All cables Power cable, Control Cable, Trailing Cable, instrumentation cables, signal cables,<br />

screened cables, es, special cables, fibre optic cables shall be supplied, laid and terminated by the<br />

Bidder as per actual site requirement.<br />

Cabling shall include laying and termination at both ends, cable trays and cable accessories for<br />

the cables to be laid by the Bidd Bidder.<br />

Bidder shall consider all required cables for cable engineering, preparation of cable schedule,<br />

terminal plans, cable support structure layout, cable layout drawings, etc. All cable trays,<br />

accessories, termination kits, glands, lugs, clamps including clamps, etc shall be included in the<br />

scope for all the cables (to be supplied by the Successful Bidder) interconnecting both side<br />

equipment or one side equipment of the Bidder’s scope.<br />

All drives shall be controlled and monitored at existing WT SYSTEM control room from the PLC.<br />

Bidder shall include PLC and all the interfacing/ interconnecting cabling and cable trays. All<br />

Cables required for this interfacing, shall be supplied and laid by the Bidder. Copper power<br />

cables, if required by the bidder, shall also be under scope of supply and laying of the bidder.<br />

Ampere meters for all conveyor belts are to be installed at the control room for monitoring<br />

the current of each drive.<br />

Bidder shall consider numeric PLC and type of Inputs / Outputs (I/Os) required for WT system<br />

for smooth and trouble free operation of various drives / mechanism from the WT SYSTEM<br />

control room. Sufficient number of I/Os in PLC extension shall be considered as per act actual<br />

requirement. Exact number and type of I/Os shall be decided during detailed engineering<br />

based on approved schemes.<br />

Bidder shall also consider sufficient number of I/Os in PLC control and monitoring for electrical<br />

power distribution system for the electrical power distribution system starting from 33KV till<br />

the down most voltage level.<br />

New PLC of WT shall be interfaced with existing PLC of Coal Handling Plant for operation of BC<br />

– 115 and BC – 103.<br />

The earthing system shall be provided for compl complete ete WT SYSTEM plant. The new earthing<br />

system shall be connected to the existing earthing system.<br />

Bidder shall also consider earthing of following equipment:<br />

Technical Specification:Sec-6, Electrical<br />

• 33kv substation equipments.<br />

• WT LT distribution transformers – Neutral as well as body earthing<br />

• 415 5 WT SYSTEM PCC at WT SYSTEM substation in switchgear cum MCC room<br />

• Control panel for power distribution equipment at existing WT control room<br />

• LT busducts<br />

• Charger panels, DCDB, etc at WT substation in switchgear cum MCC room<br />

• Underground eart mat.<br />

Page 7 of 97