The acceptance test on the system shall be carried out by the supplier as per mutually agreed<br />

test procedures to establish satisfactorily functioning of the system as a whole and each<br />

equipment as part of the system.<br />

Site Tests<br />

The tests to be carried out on the equipment at pre pre-commissioning commissioning stage shall include<br />

following but not limited to the following:<br />

MCC<br />

1. IR test before and after HV test.<br />

2. HV test with 2.5 kV megger<br />

3. Functional test for all feeders<br />

4. Testing and calibration of all meters<br />

5. Checking and calibration of protective relays as per supplier's commissioning manuals<br />

6. Check operation of contactors from local and remote points<br />

7. Checking of interlockings between incomers/bus coupler and other feeders.<br />

8. Test to prove interchangeability of similar parts<br />

9. Tests to prove correct operation of breakers at minimum and maximum specified<br />

control voltages<br />

10. Checking of earthing connection fo for neutral-earth earth bus, cable armour, location of E/F CT<br />

etc. as per the scheme.<br />

11. Check test, service and drawout position of all the breakers and operations of<br />

mechanical flag indicator and electrical indication lamps.<br />

12. Check functioning of various elect. sc schemes hemes like autochangeover signalling etc.<br />

13. Breaker : IR value checking with breaker ON. Phase to phase & phase to earth and<br />

between phases in off position<br />

MOTORS<br />

1. IR test of stator and rotor windings.<br />

2. Ensure that checking/testing of associated switchboard<br />

switchboard, , cables, relays /meter<br />

interlocks as mentioned in relevant are completed.<br />

3. Check tightness of cable connection<br />

4. Winding resistance measurement of stator and rotor.<br />

5. Checking continuity of winding.<br />

6. Check tightness of earth connections.<br />

7. Check space heaters and carryout heating of winding (if required)<br />

8. Check direction of rotation in de de-coupled coupled condition during kick start<br />

9. Measure no load current for all phases.<br />

10. Measurement of temperature of body during no load and load conditions.<br />

11. Check for tripping of motor from local/remote switches and from<br />

electrical/technological protection.<br />

12. Checking of vibration<br />

13. Checking of noise level<br />

14. Shaft voltage measurement (if required)<br />

15. Tan delta test, if required<br />

Technical Specification:Sec-6, Electrical<br />

Page 83 of 97