or as directed by the Engineer. The bottom of all excavations shall be trimmed to required<br />

levels and when excavation is carried below such levels by error, it shall be brought back to<br />

the specified level by filling with concrete of nominal mix 1 : 3 : 6 ( (cement: cement: coarse sand: 40<br />

mm down aggregates ), as directed by the Engineer. The Contractor shall ascertain for<br />

himself the nature of materials to be excavated and the difficulties, if any, likely to be<br />

encountered in executing this work. Cofferdams, sheet ppiling,<br />

iling, shoring, bracing to maintain<br />

suitable slopes, draining etc. shall be provided and installed by the contractor, to the<br />

satisfaction of the Engineer. Surplus excavated materials shall be disposed off by the<br />

contractor at locations within plant boundary wall as directed by the engineer. The<br />

Contractor shall have to constantly pump out any water collected in excavated pits and<br />

other areas due to rain water, springs etc. and maintain dry working conditions at all times<br />

until the excavation, placement of reinforcement, shuttering, concreting, Backfilling is<br />

completed. The Contractor shall remove all slush/muck from the excavated areas to keep<br />

the work area dry. The Contractor, if required, shall employ sludge pumps, for this purpose.<br />

15.2 Excavation avation in rock<br />

For the work of excavation in rock, Contractor shall engage specialized agency having<br />

experience of excavation in rock involving wedging and blasting. The agency shall be subject<br />

to approval of Engineer and the Contractor shall furnish det details ails of relevant experience in<br />

support while seeking approval for the agency agency. Only Control Blasting shall be resort resorted to<br />

with the written permission of the Engineer. In case blasting method can not be adopted<br />

considering the safety aspect of the existing rrail<br />

ail network, buildings, structures etc, hard rock<br />

shall be excavated by using expansive chemical or any other suitable means means. All the<br />

statutory laws, (Explosives Act etc.) rules, regulations, Indian Standards etc. pertaining to the<br />

acquisition, transport, storage, handling and use of explosives etc. shall be strictly followed.<br />

The contractor shall obtain Licenses from Competent Authorities for undertaking blasting<br />

work as well as for procuring, transporting to site and storing the explosives as per<br />

Explosives es Act. The Contractor shall be responsible for the safe transport, use, custody and<br />

proper accounting of the explosive materials. Surplus excavated materials shall be disposed<br />

off by the contractor at locations within plant boundary wall as directed by th the engineer.<br />

The Contractor shall have to constantly pump out any water collected in excavated pits and<br />

other areas due to rain water, springs etc. and maintain dry working conditions at all times<br />

until the excavation, placement of reinforcement, shuttering shuttering, , concreting, backfilling is<br />

completed.<br />

15.3 De-watering watering of Deep Excavations<br />

For deep underground structures like wagon tippler hopper, machinery hatches, tunnels and<br />

underground transfer houses, requiring open excavation with extensive de - watering,<br />

completely letely dry working conditions during excavation, shuttering, placement of<br />

reinforcement, concreting, water proofing of structures, backfilling and any other operation<br />

shall be maintained by suitable de - watering method of suitable capacity.<br />

15.4 Backfilling, ng, Disposal and Stacking of materials<br />

Backfilled earth shall be compacted to minimum 90 % of the standard proctor density at<br />

OMC. Sand filling shall be compacted to minimum 80 % of the relative density. However, the<br />

backfill under the rail lines and roads shall be compacted to minimum 95 % of the standard<br />

proctor density at OMC unless otherwise stated by rail Authorities. The contractor is<br />

required to excavate upto any depth as shown on the drawings or as directed by the<br />

Engineer. Lifting of excavated mate materials rials shall be done either by manual or mechanical or<br />

both means if called for by the Engineer. The disposal / stacking areas for excavated<br />

materials shall be indicated by the Engineer. If directed by the Engineer this material shall be<br />

used directly for filling illing purposes. For leads exceeding 500 m the Contractor shall transport<br />

the excavated materials by mechanical means only and as directed by the Engineer. The<br />

Contractor may be allowed to carry materials through Kuccha roads. Providing and<br />

Technical Specification:Sec-7, Civil<br />

Page 12 of 21