power to different worksites. This arrangement shall however, be coordinated and<br />

laid with approval of the Engineer. Any change in the alignment of the Contractor’s<br />

distribution lines necessitated by his work or another work must be done at<br />

Contractor’s cost. The Engineer also reserves the right to change the location of<br />

point of supply whether necessitated by his work or another work and the<br />

Contractor shall make his own arrangement at his own cost for extending his<br />

distribution line to the new location of supply point. A 3 phase armored cable shall<br />

be used by the Contractor for connecting their equipment to Purchaser’s point<br />

supply.<br />

(III) The Purchaser shall not however, guarantee the supply of electricity and no<br />

compensation for any failure or short supply of electricity will be entertained and<br />

this does not relieve the Contractor of his responsibility for timely completion of the<br />

work as stipulated in the Contract.<br />

(IV) It shall be the responsibility of the Contractor to provide and maintain the complete<br />

installation on the load site of the supply with due regard to safety requirement at<br />

site. All cabling, equipment, installations etc. shall comply in all respects with the<br />

latest statutory requirements and safety provisions, i.e. as per given in the<br />

Central/State Electricity Acts and Rules etc. The Contractor will ensure that his<br />

equipment and Electricity wiring etc. are installed, modified and maintained by a<br />

licensed Electrician / Supervisor and before power is supplied, a test certificate is<br />

to be produced to the Engineer for his approval.<br />

(V) At all times, IEA Regulations shall be followed failing which the Purchaser has a<br />

right to disconnect the power supply without any reference to the Contractor. No<br />

claim shall be entertained for such disconnection by the Engineer. Power supply<br />

will be reconnected only after production of fresh certificate from authorized<br />

electrical supervisors.<br />

(VI) The Purchaser will not liable for any loss or damage to the Contractor’s equipment<br />

as a result of variation in voltage or frequency or interruption of power supply or<br />

other loss to the Contractor arising there from.<br />

(VII) The Contractor shall ensure that the Electrical equipment installed by him are such<br />

that average power factor does not fall below 0.9 at this premises. In case P.F.<br />

falls below 0.9 in any month, he will reimburse to the purchaser at the rate same<br />

as OSEB’s rate for per unit fall of P.F. determined from time to time by Purchaser<br />

all units consumed during the month.<br />

(VIII) The power supply required for Contractor’s colony near the plant site will be<br />

determined by the Purchaser and shall be provided as per State Electricity Board’s<br />

Rules and other Statutory provisions applicable for such installations from time to<br />

time. In case of power supply to Contractor’s colony, the power will be made<br />

available at a single point and the Contractor shall make his own arrangement at<br />