(I) Loads at which tests will be conducted.<br />

(II) Time and durations of each test.<br />

(II) Instrument locations shown by a schematic diagram for each test. (Calibration certificates<br />

for each instrument shall be furnished before commencement of test).<br />

(IV) All formulas, calculations, conversion factors, correction curves, etc. to be used for test<br />

conductance.<br />

(V) Sample test report forms, and data sheet that will be used to record test results and<br />

valuation of final results.<br />

On completion of all tests, the overall efficiency of the plant shall be determined in accordance with<br />

the procedure mutually agreed upon between the Contractor and the Engineer unless otherwise<br />

covered under the Standards and Specification.<br />

In all cases, where the contract provides for test at the site, the Purchaser, except where otherwise<br />

specified, shall provide, free of charge, such labor, materials, fuel, water, electricity, lubricants as<br />

may be required from time to time and as may reasonably be demanded to carry out such tests of<br />

the plant, material or workmanship in accordance with the contract. Any special apparatus and<br />

precision instruments required for site test shall be provided by the Contractor.<br />

If for any reason, other than the fault of the contractor performance and acceptance tests for any<br />

unit shall not be carried out within sixty (60) days of notice by the Contractor to the Purchaser of<br />

the unit being ready for tests, then the Purchaser will issue an acceptance certificate on the last<br />

day of such period and payments due to the Contractor on acceptance shall be made, but<br />

nevertheless the Contractor, shall if called upon to do so by the Purchaser, within a period twelve<br />

(12) months from the said last date, make the said tests on the same terms as provided in the<br />

contract.<br />

22.00 TAKING OVER<br />

Upon successful completion of all the tests to be performed at site on equipment and systems<br />

furnished and erected by the Contractor, the Engineer shall Issue to the Contractor a taking over<br />

certificate as a proof of the final acceptance of the equipment. Such certificate shall not relieve the<br />

Contractor of any of his obligations which otherwise survive by terms and conditions of the contract<br />

after issuance of such certificate.<br />

23.00 REJECTION OF DEFECTIVE PLANT<br />

If the completed plant or any portion thereof, it is taken over under the clause ‘Taking Over’, be<br />

found defective or fails to fulfill the requirements of the contract, the Engineer shall give the<br />

Contractor notice selling forth particulars of such defects or failure, and the Contractor shall forth<br />

Tender Documents Commercial (Indigenous) Page 22 of 56