conditions for start and tripping of various drives shall be provided as per approved logic<br />

diagrams.<br />

A dedicated ed hardwired control panel / desk shall also be provided by the bidder at WT control<br />

room to control and monitor electrical power distribution system.<br />

Controls of all equipments of wagon tippler including conveyor’s all interlocks shall be PLC<br />

based. The PLC system shall be latest version having dual redundant processor with HMI based<br />

control station. There shall be two HMI control system with one operating station and other<br />

an engineering station. The system shall be designed with 10% extra input/output pprovision.<br />

Input/output of PLC(analog & digital) shall have at least 10% extra channel wired up to TB TBs in<br />

the panels. A portable programming station (Laptop) with all the ladder logic/<br />

programming/software shall be provided for engineering and troubleshooti<br />

troubleshooting functions. The<br />

system shall be capable of communicating with the existing PLC system of the CHP(The<br />

existing PLC is of GE Fanuc make make- Model 90-30,CPU-370). 370). The vendor shall be responsible for<br />

communicating and displaying the important parameters of wago wagon n tippler PLC system to the<br />

existing CHP PLC through optical fibre cable. All electrical power distribution system shall be<br />

controled and monitored through PLC.<br />

PROTECTION SYSTEM<br />

Protections for the different electrical equipment are enlisted below:<br />

For Protection of LT T motor motor, comprehensive omprehensive numeric motor protection shall be provided in the<br />

switchboard.<br />

Laying of control and power cables including supply and laying of signal cables from motors to<br />

switchboard shall be in the scope of Bidder.<br />

Comprehensive ensive numeric motor protection including but not limited to the following:<br />

• Instantaneous over current protection<br />

• Differential protection (for rating above 1000 kW)<br />

• Instantaneous time over current protection in two phases and definite time delayed over<br />

current urrent alarm on the third phase<br />

• Negative phase sequence protection<br />

• Thermal overload taking -ve and +ve phase sequence into account<br />

• Earth fault<br />

• Locked rotor protection<br />

• Winding temp monitoring and alarm for rating beyond 1000 kW<br />

• Under voltage protectio protection<br />

Microprocessor based numeric motor protection relay shall also have following facilities:<br />

• Communication facility with open protocol like IEC/Modbus.<br />

• Relay should store last five fault records (minimum) with date and time stamping.<br />

• Relay should have no. o. of start menu for start inhibition.<br />

• Relay should have facility for displaying three phase and neutral current<br />

Technical Specification:Sec-6, Electrical<br />