• Guideline for wagon tipplers issued by RDSO – G33 (Rev. 1) of May 2010 with latest<br />

amendments if any.<br />

3.2.2 This Sub-section section shall be read in conjunction with Electrical Sub Sub-sections. sections.<br />

3.3 Construction and Design<br />

3.3.1 Construction<br />

Control desks/panels and annunciation system shall be provided as per the requirement of<br />

electrical Section. Annunciation’s, indications, electrical meters and instrumentation shall be<br />

provided as specified. Ammeters shall be provided on control desk for a aall<br />

motors rated 30<br />

kW and above and for all equipment.<br />

3.3.2 Design<br />

The Contractor shall provide a comprehensive control indication and annunciation scheme<br />

for the plant & equipment under wagon tippler and conveyor system package and integrate<br />

the same with the existing control & monitoring scheme of the CHP. Contractor shall furnish<br />

a block diagram and write write-up up on the scheme proposed. The final scheme will be approved by<br />

the Owner/RITES and the Contractor shall be required to execute the approved scheme scheme. In<br />

general, interlocking shall be achieved through feed feed-back back signals from field equipment. A<br />

comprehensive Annunciation and Indication scheme shall be provided such that, it will be<br />

possible for the operator to locate and identify the fault from the disp display ace of Control<br />

desk. The scheme shall include the basic remote control instrumentation, indication and<br />

annunciation requirements as per various technical specification requirements. However,<br />

the Contractor may offer any alternative proposal which he co considers nsiders to be equal, superior<br />

to the scheme as described in subsequent clauses below for achieving reliable and trouble<br />

free operation of the plant, for consideration of the Owner.<br />

4.0 OPERATION AND CONTROL PHILOSOPHY<br />

4.1 The Wagon Tippler control room sh shall all be located by the side of Wagon Tippler to<br />

accommodate control & monitoring equipment of wagon tipplers. It shall also have a battery<br />

room.<br />

4.2 The existing coal handling system is being controlled from the following control points. The<br />

existing control ol philosophy of the coal handling plant is being described below for the<br />

contractor to understand the existing system and suitably plan integration of the controls<br />

and interlocks of the proposed control system of the wagon tippler package with the existin existing<br />

system.<br />

4.2.1 Owner’s Existing Coal Handling Plant Control Room<br />

Operation of the CHP equipment is being controlled from the Owner’s CHP control room.<br />

(a.) Conveyors, feeders, flap gates, hydraulic couplings etc.<br />

(b.) Complete Dust Suppression system & sservice<br />

water system.<br />

(c.) Ventilation system (group/individual control as required).<br />

(d.) In line Magnetic separators and Suspended Magnet (ON/OFF control with indication).<br />

Technical Specification:Sec-4,System System Parameters, Operation & Control Philosophy<br />

Page 4 of 64