1. Procedure mentioned in manufacturer’s manual<br />

2. Under the expert supervision<br />

3. Sequence and plan of erection as per the guidance of Purchaser’s Site In charge or their<br />

consultant<br />

4. During erection of supplier’s equipment, existing equipment /system shall not be<br />

disturbed.<br />

5. Erection shall be in accordance with approved layout drawing and installation details.<br />

6. Cable laying shall be as per approved cable layout drawings and work shall be carried<br />

out in a neat manner.<br />

All erection-installation installation accessories required for erectio erection/installation n/installation of equipment and<br />

handling equipment required for handling of equipment from store to installation site are<br />

included in the scope of work of Bidder as a whole.<br />

Bidder shall ensure that the work erection and erected equipment shall comply wit with all<br />

statutory norms, regulations and standards applicable to the works/equipment and any<br />

additional work/equipment required, if any, shall be under scope of the Bidder.<br />

Necessary clearance from the wall shall be maintained as per IS/IE Rules from front/ front/rear/ side<br />

of all the panels inside a room.<br />

HT Power cables and LT power/control cables shall be laid in different cable trays. LT power<br />

cables and LT control cables shall also be laid in different trays, however, if necessity arises<br />

due to space constraints ints or lesser number of cables, LT power cables and LT control cables can<br />

be put on the same trays keeping sufficient gap between them. 24V DC cables, if required,<br />

shall be laid entirely in different dedicated trays.<br />

Cable trays in single tier or in mul multitier titier shall be installed in vertical arrangement everywhere to<br />

avert coal accumulation and space reduction.<br />

Fire Prevention:-<br />

Proper design and use of quality material, equipment so as to avoid overloading in<br />

Distribution board, wiring system including sub main, switch & sockets shall be ensured by the<br />

bidder.<br />

Insulating mats in front of PCC, MCC or control panel, protective rubber gloves, earth rods,<br />

artificial respiration apparatus, line man’s belt etc shall be provided in substations by the<br />

bidder.<br />

Fire re extinguishers for various switch gear location, substations, PCC, MCC suitable for<br />

electrical fire (class –C) C) like dry chemical powder, carbon carbon-dioxide, dioxide, carbon carbon-tetra chloride type<br />

shall be provided along with fire buckets filled with sands.<br />

Comprehensive fire protection system in conformity with the requirements of national<br />

building code, ECBC 2007 shall be ensured by the bidder.<br />

5.0 INSPECTION AND TESTING<br />

Technical Specification:Sec-6, Electrical<br />

Page 79 of 97