(c) The testing schedule sh shall all be prepared for systematic commissioning of individual<br />

equipment/sub-system system Commissioning. The format of testing/Commissioning schedule shall<br />

be such as to maintain consistency of presentation, content and reporting<br />

(d) The contractor shall submit the li list st of commissioning documentation to be submitted by<br />

him, alongwith their submission schedule for various equipment/systems covered under the<br />

contract, with in 6(six) month from the date of award of contract, for the acceptance of<br />

employer.<br />

(e) The Contractor r shall submit the commissioning documentation, for various<br />

equipment/covered under the contract, for the approval of employer, at least 18 months<br />

before the scheduled date of commissioning of the equipment/systems.<br />

27.0 COMMISSIONING ACTIVITIES<br />

(a) Upon completion ompletion of pre pre-commissioning commissioning activities/tests, the contractor shall initiate<br />

commissioning of facilities. During commissioning the Contractor shall carry out system<br />

checking and reliability trials on various sub sub-systems of the facilities.<br />

(b) Contractor shall carry out the checks/tests at site to demonstrate to the Employer that<br />

each of the equipment of the supplied complies with requirements stipulated and is installed<br />

in accordance with requirements specified.<br />

(c) Before the plant is put into initial opera operation tion the Contractor shall be required to conduct<br />

test to demonstrate to the Employer that each item of the plant is capable of correctly<br />

performing the functions for which it was specified and its performance, parameters etc. are<br />

as per the specified/appro<br />

specified/approved ved values. These tests may be conducted concurrently with those<br />

required under commissioning sequence.<br />

(d) Other tests shall be conducted, if required by the Employer, to establish that the plant<br />

equipment are in accordance with requirements of the specifica specifications.<br />

(e) The Contractor shall conduct all the commissioning tests and undertake commissioning<br />

activities pertaining to all other auxiliaries and equipments including all electrical<br />

equipment/systems not specifically brought out above but are within the sco scope of work and<br />

facilities being supplied and installed by the Contractor and follow the guidelines indicated<br />

above or elsewhere in these technical specifications(Section<br />

specifications(Section- VI)<br />

(f) Initial Operation<br />

Upon completion of system checking/Tests as above and as a pa part rt of commissioning of<br />

facilities, complete plant/facilities shall be put into initial operation as stipulated in General<br />

Technical Requirements.<br />

Technical Specification:Sec-8l<br />