7.2.2 Equipment Capacity<br />

Capacity of individual equipment shall be tested separately:<br />

(i) Each Wagon Tippler : 20 tips/hour (Guaranteed)<br />

(ii) Each Apron feeder : 1200 TPH (Guaranteed)<br />

7.2.3 Contractor shall also demonstrate that all intermediate equipments viz. Gates, Dust<br />

suppression, Ventilation System etc. can perform as per specification and design<br />

requirement.<br />

7.2.4 Performance and guarantee requirement of various other equipments have been elaborated<br />

elsewhere.<br />

8.0 PERFORMANCE & GUARANTEE TEST PROCEDURE<br />

In accordance with GTR the plant shall be subjected to performance and Guarantee Tests on<br />

successful completion of trial operations. Further, the performance and Guarantee Tests<br />

shall be conducted as per the guideline procedure indicated elsewhere. However, detailed<br />

procedure shall be submitted by vendor as per the guidelines for Owner Owner/RITES's approval.<br />

The P&G Test procedure shall be submitted by the bidder.<br />

8.1 Liquidated Damages for Shortfall in Performance<br />

Should the results s of the performance and guarantee tests show that the equipments /<br />

system have failed to meet the guaranteed parameters, the Contractor shall carry out<br />

modifications, if considered necessary, within 90 days of the notification by Owner.<br />

If the equipment fails ails to meet the guarantee parameters at the end of the above specified<br />

period of 90 days, Owner may at his discretion, reject the equipment or accept it after<br />

assessing the liquidated damages at rates specified herein, to be payable by the Contractor.<br />

8.2 The following equipments/streams shall be subjected to performance and guarantee test in<br />

line with the specification to prove the performance guarantee for all intermediate<br />

equipment.<br />

Liquidated Damages towards shortfall in guaranteed performance shall be imposed as % of<br />

the order value limiting to 5% against following parameters.<br />

Sl.<br />

No.<br />

Equipment<br />

1 Wagon Tippler<br />

2 Apron Feeder<br />

3 Conveyors (R1 & R2)<br />

Technical Specification Sec-2,:Intent :Intent of Specifications<br />

Guaranteed<br />

parameter<br />

Short fall LD amount to be<br />

imposed<br />

20 Tips /Hour By One tip per hour 1% of order value<br />

By two tips per Hour 2% of order value<br />

Beyond two tips per hour Rejected<br />

1200TPH By 0.5% 1% of order value<br />

By 1.0% 1.5 1.5% of order value<br />

Beyond 1.0% Rejected<br />

1200TPH By 0.5% 1% of order value<br />

By 1.0% 1’5 1’5% of order value<br />

Beyond 1.0% Rejected<br />

Page 13 of 17