c) Drawing submission schedule indicating list of all drawings with their respective titles and<br />

dates shall be submitted to the Purchaser. The schedule shall also indicate the latest date<br />

by which Contractor shall furnish all design calculations. The schedule shall be amended<br />

or extended by the Contractor in consultation with the Purchaser as and when necessary.<br />

15.03 Within a stipulated time period the Contractor shall submit for approval of the Purchaser the<br />

following drawings and technical data:<br />

a) Dimensional layout drawings of the plant and equipment to be supplied under the contract<br />

and all certified data relating to the design on foundation structures to enable the<br />

Purchaser to arrange for construction of the necessary foundations and civil works.<br />

All information regarding material and size of anchor bolt, nuts, sleeves, inserts and<br />

supports which shall have to be embedded in concrete shall be furnished in the detailed<br />

foundation drawing.<br />

b) Dimensional drawings showing individual equipment being supplied under the contract,<br />

method and sizes of connections to the Purchaser’s other equipment, giving also the limits<br />

of variations of the dimensions.<br />

c) All efficiency and characteristic curves required under the specification.<br />

d) Schematic drawings of all wirings, connections and interlocking diagrams showing the<br />

points where the connections have to be made by the Purchaser.<br />

e) Necessary structural and other calculations and data required for demonstrating fully that<br />

all parts of the equipment to be furnished shall conform to the provisions and intent of the<br />

contract.<br />

The Contractor shall submit six (6) prints of each drawing for approval. Two (2) prints shall be<br />

forwarded to the Purchaser and four (4) prints shall be forwarded to the Consulting Engineer.<br />

When prints of drawings have been marked “Approved except as noted, Resubmission required”<br />

the Contractor shall make necessary corrections and again submit corrected copies for approval as<br />

per details stipulated. Further revision will be shown by number, date and subject in a revision<br />

block.<br />

Upon receipt of the prints which have been marked “Approved” or “Approved except as noted:<br />

Forward Final drawing” the Contractor shall furnish within a reasonable time fourteen (14)<br />

additional prints of each of drawings and one (1) reproducible transparency after minor corrections,<br />

if any, to the Purchaser.<br />

Relevant civil construction drawings if felt necessary by Consulting Engineer, shall be forwarded to<br />

the Contractor in triplicate. He shall review incorporation of information furnished by him, such as,<br />