Tender Notice No. - …………..............<br />

interfere with the layout and progress of other construction works. Supply of water shall be<br />

charged from Contractor at the rates prevailing at Site.<br />

Contractor shall ensure that there is no wastage of water. On completion of the work, the<br />

Contractor shall remove all such work and shall reinstate and make good any work<br />

disturbed to the satisfaction of the Engineer.<br />

(b) Cranes, if available, will be provided by Owner on payment of rent to the Owner.<br />

5.3 Work and Services to be provided by the Contractor<br />

The following work and services shall also be provided under the contract :<br />

(i) Material transportation to erection site at Contractor’s risk and cost.<br />

(ii) All construction activities to complete the plant as per the specifications agreed by the<br />

Owner. The activities shall be included but not limited to building structures, rooms,<br />

foundations for equipments and accessories and stack etc.<br />

(iii) Labor license for contractor and sub-contractor’s labor if required / applicable as per State<br />

Govt.<br />

5.4 Owner’s Lien on Equipments<br />

The Owner shall have lien on all equipments including those of the Contractor brought to the Site<br />

for the purpose of construction, erection, testing and commissioning of the plant. The Owner shall<br />

continue to hold the lien on all such equipments throughout the period of Contract. No material<br />

brought to the Site shall be removed from the Site by the Contractor and / or his Sub-contractors<br />

without the prior written approval of the Owner.<br />

5.5 Protection of Work<br />

The contractor shall have total responsibility for protecting his Works till it is finally taken over by<br />

the Owner. No claim will be entertained by the Owner or the Consultant for any damage or loss to<br />

the Contractor’s Works and the Contractor shall be responsible for the complete restoration of the<br />

damaged works to its original condition to comply with the specifications and drawings. Should any<br />

such damage to the Contractor’s Works occur because of other party not under his supervision or<br />

control, the Contractor shall make his claim directly with the party concerned. If disagreement or<br />

conflict or dispute develops between the Contractor and the party or parties concerned regarding<br />

the responsibility for damage to the Contractor’s Works the same shall be resolved as per the<br />

provisions of the clause entitled ‘Co-operation with other Contractors’. The Contractor shall not<br />

cause any delay in the repair of such damaged works because of any delay in the resolution of<br />

such disputes. The Contractor shall proceed to repair the work immediately and no cause thereof<br />

will be assigned pending resolution of such dispute.<br />