44.18 Construction Management<br />

(a) The field activities of the Contractors working at site will be coordinated by the Engineer<br />

and the Engineer’s decision shall be final in resolving any disputes or conflicts between the<br />

contractors and tradesmen of the Purchaser regarding scheduling and co-ordination of<br />

work. Such decision by the Engineer shall not be a cause for extra compensation or<br />

extension of time for the Contractor.<br />

(b) The Engineer shall hold weekly meetings of all the Contractors working at site, at a time<br />

and a place to be designated by the Engineer. The Contractor shall attend such meetings<br />

and take notes of discussions during the meeting and the decisions of the Engineer and<br />

shall strictly adhere to those decisions in performing his works. In addition to the above<br />

weekly meetings, the Engineer may call for other meetings either with individual<br />

contractors or with selected number of contractors and in such a case the Contractor, if<br />

called, will also attend such meetings.<br />

(c) Time is the essence of the Contract and Contractor shall be responsible for performance of<br />

his woks in accordance with the specified construction schedule. If at anytime, the<br />

Contractor is falling behind the schedule, he shall take necessary action to make good for<br />

such delays by increasing his work to comply with the schedule and shall communicate<br />

such actions in writing to the Engineer, satisfying that his action will compensate for the<br />

delay. The Contractor shall note be allowed any extra compensation for such action.<br />

(d) The Engineer shall however not be responsible for provision of additional labor and/ or<br />

materials or supply or any other services to the Contractor except for the co-ordination<br />

work between various entities as set out earlier.<br />

44.19 Safety Regulations<br />

(a) Without prejudice to the general obligation under the statutes the Contractor shall ensure<br />

the safety of all the workmen, materials and equipment either belonging to his or to others<br />

working at site.<br />

b) The Contractor will notify the Engineer of his intention to bring on to site any equipment or<br />

any container, with liquid or gaseous fuel or other substance which may create hazard.<br />

The Engineer shall have the right to prescribe the conditions under which such equipment<br />

or container may be handled and used during the performance of the works and the<br />

Contractor shall strictly adhere to such instructions. The Engineer shall have the right to<br />

inspect any construction plant and to forbid its use, if in his opinion it is unsafe. No claim<br />

due to such prohibition shall be entertained by the Purchaser.<br />

Tender Documents Commercial (Indigenous) Page 48 of 56