(h) Packaging or shipping units shall be designed within the limitations of unloading facilities<br />

and the equipment which will be used for transport. Complicatio Complications ns involved with ocean<br />

shipment and the limitations of ports, railways and roads shall be considered. It shall be the<br />

Contractor's responsibility to investigate these limitations and to provide suitable packaging<br />

to permit safe handling during transit and at the job site.<br />

(i) Electrical equipment, control and instrumentation shall be protected against moisture and<br />

water damage. All external gasket surfaces and flange faces, couplings, motor pump shafts,<br />

bearing and like items shall be thoroughly cleaned and coa coated ted with rust preventive<br />

compound as specified above and protected with suitable wood, metal or other substantial<br />

type covering to ensure their full protection.<br />

(j) Equipment having antifriction or sleeve bearings shall be protected by weather tight<br />

enclosures.<br />

(k) Coated surfaces shall be protected against impact, abrasion, discolouration and other<br />

damage. Surfaces which are damaged shall be repaired.<br />

(l) All exposed threaded parts shall be greased and protected with metallic or other substantial<br />

type protectors. All female threaded openings shall be closed with forged steel plugs. All<br />

pipings, tubing, and conduit equipment and other equipment openings shall be sealed with<br />

metallic or other rough usage covers and tapped to seal the interior of the equipment<br />

piping, tubing, ing, or conduit.<br />

(m) Provisions shall be made to ensure that water does not enter any equipment during<br />

shipment or in storage at the plant site.<br />

(n) Returnable containers and special shipping devices shall be returned by the manufacturer's<br />

field representative at the Contractor's expense.<br />

(o) While packaging the material, care shall be taken for the limitation from the point of view of<br />

availability of railway wagon sizes in India.<br />

44.3 Equipment Installation<br />

(a.) General Requirements<br />

The Contractor shall furnish all construction materials, tools and equipment and shall perform<br />

all work required for complete installation of all control and instrument equipment furnished<br />

under this specification. Contractor shall prepare detailed install installation ation drawings for each<br />

equipment furnished under this specification for Employer's approval. Installation of all<br />

equipment/systems furnished by this specification shall be as per Employer's approval.<br />

Erection procedures not specified herein shall be in ac accordance cordance with the recommendations of<br />

the equipment manufacturers. The procedures shall be acceptable to the Employer. The<br />

Contractor shall coordinate his work with other suppliers where their instruments and devices<br />

are to be installed under specifications<br />

specifications.<br />

(b.) Installation Materials<br />

All materials required for installation, testing and commissioning of the equipment shall be<br />

furnished by the Contractor.<br />

(c.) Regulatory Requirements<br />

Technical Specification:Sec-8l<br />

Page 22 of 23