41.00 EFFECT & JURISDICTION OF CONTRACT<br />

41.01 The contract shall be considered as having come into force from the date of the acceptance of<br />

Letter of Intent.<br />

41.02 The laws applicable to this contract shall be in the laws in force in India. The courts of Orissa shall<br />

have exclusive jurisdiction in all matters arising under the contract.<br />

42.00 TIME IS THE ESSENCE OF CONTRACT<br />

42.01 The time and the date of completion of the works as stipulated in the contractor’s proposal and<br />

accepted by the owner without or with modifications, if any, and so incorporated in the Letter of<br />

Intent, shall be deemed to be the essence of the contract. The Contract shall so organize his<br />

resources and perform his work as to complete it not later than the date agreed to.<br />

42.02 The Contractor shall submit a detailed PERT Network within the time frame agreed above covering<br />

various key phases of the works such as design, procurement, manufacturing, shipment and field<br />

erection activities within thirty (30) days after the date of Letter of Intent. This network shall also<br />

indicate the interface facilities to be provided by the Owner and the dates by which such facilities<br />

are needed.<br />

Contractor shall discuss the network so submitted with the owner. The agreed network which may<br />

be in the form as submitted or in revised form in line with the outcome of discussions shall form<br />

part of the Contract to be signed within sixty (60) days from the date of acceptance of Letter of<br />

Intent. During the performance of the contract, if in the opinion of the Engineer proper progress is<br />

not maintained suitable changes shall be made in the contractor’s operations to ensure proper<br />

progress.<br />

42.03 The above PERT network shall be reviewed and periodic review reports shall be submitted by the<br />

Contractor as directed by the Engineer.<br />

42.04 Within a month of the award of the contract, the Contractor shall make available to the Engineer, a<br />

detailed manufacturing programme, in line with the agreed contract network. Such manufacturing<br />

program shall be reviewed, updated and submitted to the Engineer once every two months<br />

thereafter.<br />

43.00 ERECTION SUPERVISION SERVICES<br />

The Contractor, if required by the Purchaser, shall furnish the services of one or more supervisors,<br />

to render technical advice, assistance and guidance to the Purchaser in connection with the<br />

erection and/or commissioning of equipment subject to the provisions herein after set forth. In case<br />

of complete erection of plant and materials such services shall automatically be included in the<br />

scope of the Contractor and no extra charges shall be applicable.<br />