approach/maintenance platforms, handling for equipment, civil and structural works and<br />

necessary accessories shall be provided for WT hopper top & all transfer points, etc.<br />

16.2.2 Sump Pump<br />

4x100% sump pumps alongwith level switches and piping up to nearest Owner's drain (max.<br />

up to 50.0 meters from outside the building) shall be provided at all locations wherever<br />

natural drainage is not possible. Sump pumps along with drain pits shall be provided at other<br />

locations also, if required, during detailed engineering stage. Sealing pumps with valves,<br />

piping fittings and other accessories for sealing of sump pumps shall be provided.<br />

16.2.3 Service Water System<br />

Service water distribution system complete with water supply system, valves, quick<br />

couplings, hose pipes with nozzle, piping, pumps, drive motors with canopy, couplings with<br />

enclosure, electricals, including supporting structures, handling for equipment’s, civil and<br />

structural works and necessary accessories shall be provided throughout the coal handling<br />

plant area in Contractor’s scope.<br />

16.2.4 Pipings, Fittings, Valves and Specialities<br />

The material to be supplied for completing the pipe work shall include but not be limited to<br />

the following :<br />

(1) Straight piping, bends, tees, elbows, branches, laterals, crosses, reducing unions,<br />

couplings, caps, blank flanges, saddles etc. necessary for making reliable piping system.<br />

(2) Gaskets, ring joints, ints, jointing material etc. as required.<br />

(3) Instrument tapping connections, stubs.<br />

(4) Gate, globe and check valves to start/stop, regulate and to prevent back flow.<br />

(5) Duplex Strainers.<br />

(6) Anchors, hangers and supports as required including secondary steel embedments etc.<br />

(7) Bolts, nuts, fasteners as required for interconnection piping, valves and fittings as well<br />

as for terminal points.<br />

(8) The entire water piping of DS/SW/PW/CW shall be routed/supported on concrete<br />

pedestal and conveyor galleries. Whereever the layout does not permit the pipes to be<br />

routed over ground, the same shall be buried in conformity to the relevant standards &<br />

shall be provided with necessary protective coating as per relevant standards.<br />

(9) Painting, anti-corrosive corrosive coatings etc. inside and outside pipe pipes s as necessary.<br />

(10) Welding electrodes and welding rods.<br />

(11) The area around storage tanks strainers, two valves etc. (located out side pump house)<br />

shall be paved with drains.<br />

16.3 Terminal Points<br />

Owner shall provide supply of water for dust suppression system, service water, potable<br />

water at one terminal point as elaborated elsewhere. Beyond the terminal point, the<br />

complete pipe work along with associated valves, specialities, instruments, fittings and<br />

Technical Specification:Sec-4,System System Parameters, Operation & Control Philosophy<br />

Page 35 of 64