the site. Illumination of wagon tippler and the conveyor area shall be the scope of the<br />

tenderer.<br />

18.3 Water<br />

Contractor shall make all arrangements himself for the supply of construction water as well as<br />

potable water for labour and other personnel at the worksite/colony.<br />

18.4 Communication<br />

The Employer will extend the telephone facilities, if available at Site, for purpos purposes of Contract.<br />

The Contractor shall be charged at actuals for such facilities.<br />

19.0 FACILITIES TO BE PROVIDED BY THE CONTRACTOR<br />

19.1 Contractor's site office Establishment<br />

The Contractor shall establish a site office at the site and keep posted an autho authorized<br />

representative for the purpose of the contract, pursuant to GCC.<br />

19.2 Tools, tackles and scaffoldings<br />

The Contractor shall provide all the construction equipments, tools, tackles and scaffoldings<br />

required for pre-assembly, assembly, installation, testing, commissioning and conducting Guarantee<br />

tests of the equipments covered under the Contract. He shall submit a list of all such materials<br />

to the Employer before the commencement of preassembly at Site. These tools and tackles<br />

shall not be removed from the Si Site te without the written permission of the Employer. The<br />

Contractor shall arrange Dozer, Hydra, Cranes, Trailer, etc. for the purpose of fabrication,<br />

erection and commissioning.<br />

19.3 Testing Equipment and Facilities:<br />

The contractor shall provide the necessa necessary ry testing, equipment and facilities.<br />

19.4 Site laboratory for civil works:<br />

Contractor shall provide and maintain a site laboratory for the testing of construction material<br />

under the direction and general supervision of employer.<br />

19.5 First-aid<br />

19.5.1 The Contractor shall provide necessary first first-aid aid facilities for all his employees, representatives<br />

and workmen working at the Site. Enough number of Contractor’s personnel shall be trained<br />

in administering first-aid.<br />

19.5.2 The Employer will provide the CContractor,<br />

ontractor, in case of any emergency, the services of an<br />

ambulance for transportation to the nearest hospital.<br />

19.6 Cleanliness<br />

19.6.1 The Contractor shall be responsible for keeping the entire area allotted to him clean and free<br />

from rubbish, debris etc. during the period of Contract. The Contractor shall employ enough<br />

number of special personnel to thoroughly clean his work work-area area at least once in a day. All such<br />

rubbish and scrap material shall be stacked or disposed in a place to be identified by the<br />

Technical Specification:Sec-8l<br />

Page 7 of 23