21.00 TESTS ON COMPLETION AND TRIAL RUN AT SITE<br />

Where possible all tests shall be carried out before dispatch. Should, however, it become<br />

necessary for the final tests as to performance and guarantees to be held over until the plant is<br />

erected at site, they shall be carried out as per agreed procedure within two (2) months or such<br />

time as may be considered reasonable by the Purchaser after commissioning of the equipment.<br />

Inspection and test at site during erection and on completion of erection shall be carried out on any<br />

plant and equipment to satisfy the guaranteed performance of each equipment and the whole<br />

installation as set forth below:<br />

Individual equipment tests:<br />

(I) Inspection and checking of units<br />

(II) Placing in operation<br />

(II) Initial operation<br />

(IV) Reliability tests<br />

(V) Efficiency and consumption tests<br />

(VI) Load tests<br />

The sequence of tests for individual equipment shall be as mutually agreed to between the<br />

Contractor and the Engineer.<br />

Duration of the trial operation of the complete equipment shall be 30 continuous days with available<br />

wagon rakes during this period as mutually agreed and decided. The acceptance test shall be<br />

carried out within two (2) months after the trial run has been satisfactorily completed. Any delay for<br />

carrying out these works for force majeure reasons shall be given due consideration. Should the<br />

result of these tests not come within the margin specified, the test shall, if required, be repeated<br />

after necessary rectification measures recommended by the Contractor within one (1) month from<br />

the date of plant is ready for retest, and the Contractor shall repay to the Purchaser all reasonable<br />

expenses which he may be put to by such tests.<br />

The performance and acceptance tests of the complete installation shall be carried out to prove the<br />

guarantees specified for different equipment. These tests shall be made in accordance with<br />

established and approved procedures. The Contractor shall submit within reasonable time after the<br />

award of contract, detailed procedure for conductance of all tests for approval of the Engineer. The<br />

procedure shall include the following information for such test:<br />

Tender Documents Commercial (Indigenous) Page 21 of 56