6.134<br />

more than 100 times for fresh fuel. These increases must be taken into account by increased<br />

shielding and by use <strong>of</strong> remote operations and maintenance when designing fuel cycle facil-<br />

ities. Reprocessing costs would increase by an estimated 5 percent, fuel fabrication costs<br />

would double, and transportation costs would nearly triple (Smith and Davis 1980).<br />

The following cost estimates are for only the specialized partitioning facilities col-<br />

ocated with their respective mixed-oxide fuel fabrication facility and spent fuel reproces-<br />

sing facility. The fuel fabrication plant has a throughput <strong>of</strong> 660 MTHM per year and the re-<br />

processing plant a throughput <strong>of</strong> 2,000 MTHM per year.<br />

Capital Costs<br />

The partitioning process buildings are first-<strong>of</strong>-a-kind facilities that, in several<br />

instances, include process operations that have not advanced beyond laboratory test and<br />

evaluation. Therefore, considerable judgment was used in the development <strong>of</strong> the capital<br />

costs shown in Table 6.1.27.<br />

Operatings Costs<br />

Estimated operating costs are shown in Table 6.1.28. Labor cost estimates are based on<br />

an average salary <strong>of</strong> $20,000 per year for management, engineering, and supervision and<br />

$14,500 per year for operators, maintenance personnel, guards, laboratory technicians, and<br />

clerical personnel.<br />

TABLE 6.1.27. Capital Costs For Partitioning Facilities<br />

(Millions <strong>of</strong> 1978 Dollars)<br />

(Smith and Davis 1978)<br />

Colocated With Colocated With<br />

Reprocessing Plant Fuel Fabrication Plant<br />

Material Labor Total Material Labor Total<br />

Land Improvements 1.3 1.2 2.5 1.0 .9 1.9<br />

Process Facilities 200.0 127.0 327.0 73.1 46.9 120.0<br />

Tunnel and Piping 5.8 10.6 16.4 4.9 9.2 14.1<br />

Support Facilities 13.0 5.7 18.7 12.2 4.6 16.8<br />

Subtotal 220. 145 365. 91 62 153<br />

Field Indirects and<br />

S/C's OH&P 145 62<br />

Subtotal 510 215<br />

Engineering & Design 143 60<br />

Subtotal 653 275<br />

Contingency 228 96<br />

Total 881 371