SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS: continued<br />

deficiencies corrected by the appropriate Subs, with facilities staff and the CA witnessing. Any<br />

final adjustments to the O&M manuals and as-builds due to the testing will be made.<br />

3.8 ENHANCED COMMISSIONING<br />

A. The CA will review GC submittals applicable to systems being commissioned (see Part 1.6 <strong>of</strong><br />

this section) for compliance with the Owner’s project requirements and basis <strong>of</strong> design.<br />

B. The CA will develop a systems manual that provides future operating staff the information<br />

needed to understand and optimally operate the commissioned systems.<br />

C. The CA will verify that the requirements for training operating personnel and building<br />

occupants have been completed.<br />

D. The entire Commissioning Team (see Part 1.3 <strong>of</strong> this section) will be involved in reviewing the<br />

operation <strong>of</strong> the building with operations and maintenance (O&M) staff and occupants within<br />

10 months after substantial completion. A plan for resolving any outstanding commissioningrelated<br />

issue will be developed and implemented by this Commissioning Team.<br />

END OF SECTION 019113<br />