18.12.2012 Views

university of illinois - UIHistories Project

university of illinois - UIHistories Project

university of illinois - UIHistories Project

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

70 BOARD OF TRUSTEES [September 18<br />

versity with a release <strong>of</strong> all claims and waiver <strong>of</strong> all liens from Crouch-Walker<br />

Company (a partnership hereinafter termed "Crouch-Walker"), one <strong>of</strong> Warren's<br />

subcontractors, as is required by the contract between Warren and the University<br />

and for the University's protection. Crouch-Walker claims that a balance<br />

<strong>of</strong> $36,620.50 is due it from Warren under the contract between them, and also<br />

claims that it sustained damages, consisting principally in increased costs it<br />

alleges it incurred, in the sum <strong>of</strong> $66,265.69 in consequence <strong>of</strong> delay in the<br />

completion <strong>of</strong> its work, for which Crouch-Walker asserts both Warren and the<br />

University are legally liable. Warren claims that the balance due Crouch-Walker<br />

from Warren under the contract between them is less than the amount claimed<br />

by Crouch-Walker and denies that it is under any liability to Crouch-Walker in<br />

connection with the latter's said claim for damages.<br />

Completion <strong>of</strong> the building was delayed, for various reasons, until more than<br />

two years subsequent to the date originally contemplated by the contract. Warren<br />

and four <strong>of</strong> the other prime contractors also assert claims for damages in substantial<br />

sums against the University because <strong>of</strong> increased costs they claim they<br />

incurred because <strong>of</strong> the delay. The University has denied liability to any <strong>of</strong> these<br />

contractors upon these claims because it and the architects are <strong>of</strong> the opinion<br />

that the University was not responsible for the delay in the completion <strong>of</strong> the<br />

building, the major portion <strong>of</strong> the responsibility for which the University and<br />

the architects assert is properly attributable to Warren. Some <strong>of</strong> the prime<br />

contractors asserting said claims for damages have also indicated that they<br />

believe Warren to be largely responsible for the delay in the completion <strong>of</strong> the<br />

building, but assert that the University is legally liable to them for the same<br />

upon the theory that Warren was the University's agent in doing the work<br />

contemplated by the contract between Warren and the University. Warren and<br />

Crouch-Walker apparently assert that a portion <strong>of</strong> the delay in the completion<br />

<strong>of</strong> the building is attributable to said other prime contractors, but also assert that<br />

the University is liable to them therefor upon the same theory.<br />

The University denies liability upon its part in connection with all <strong>of</strong> the<br />

foregoing claims, but, in the event it should be held liable with respect to any<br />

<strong>of</strong> them, it asserts that it has the legal right to recover for what it may thus<br />

be compelled to pay from the contractor or contractors found to be responsible<br />

for the delay.<br />

Repeated efforts upon the part <strong>of</strong> University <strong>of</strong>ficers to negotiate a settlement<br />

disposing <strong>of</strong> Crouch-Walker's claims, which might enable the University to<br />

also dispose <strong>of</strong> the other claims, have proven unsuccessful to date with the<br />

result that on September 6, 1956, Crouch-Walker instituted a suit in the Circuit<br />

Court <strong>of</strong> Cook County against Warren, the University, and Seaboard Surety<br />

Company, one <strong>of</strong> the sureties upon the performance bond given the University<br />

by Warren, in which Crouch-Walker prays judgment against all <strong>of</strong> said defendants<br />

in the sum <strong>of</strong> $135,000, the aggregate <strong>of</strong> Crouch-Walker's above mentioned<br />

claims plus interest at 5 per cent per annum from April 27, 1953, the date upon<br />

which Crouch-Walker claims it completed its work under its contract with<br />

Warren. Summons in that suit has been served upon the University, and the<br />

latter must file an appropriate pleading in the suit on or before October 14.<br />

Even if the suit can be and is confined to the claims asserted by Crouch-<br />

Walker, the litigation it will entail will be rather extensive, protracted, and<br />

expensive. It appears unlikely, however, that the suit can or will be confined to<br />

those claims, since it is reasonably to be anticipated that, in addition to defending<br />

against Crouch-Walker's claims therein, Warren will probably assert its own<br />

claims against the University in the suit and thereby broaden the issues in it to<br />

the extent that the University may find it necessary or desirable to bring the<br />

other prime contractors into the suit so that all <strong>of</strong> the claims asserted against<br />

the University, and those asserted by it, arising out <strong>of</strong> the construction <strong>of</strong> the<br />

Research and Educational Hospitals Addition and the delay in its completion will<br />

then be litigated in this proceeding.<br />

While the Legal Counsel will appear for and represent the University in this<br />

litigation he will be unable, because <strong>of</strong> his other duties, to devote to it much <strong>of</strong><br />

the time and work which will be required. Moreover, past experience has demonstrated<br />

that it is necessary for him to have the assistance <strong>of</strong> special counsel.<br />

practicing in Chicago, in cases in the Cook County courts to which the University<br />

is a party. This is true, even though the present suit, notwithstanding the

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!