Progress Review Meeting<br />

Page 2<br />

* DDI and WCH to discuss tank ladder fall protection requirements. DDI to propose providing<br />

JLG, manlift, etc. in process. WCH has this proposal for review. DDI to provide revision to the<br />

plan as part of the change notice proposal.<br />

" Electrical Drawings for electrical tie-ins, as-builts and diesel tank electrical design have been<br />

submitted to WCH. Review and comments to be returned to RDC today.<br />

* WCH requested status of Cold Weather Protection plan from DDI. WCH has returned submittal<br />

with comments. DDI does not plan to resubmit incorporation of the cold weather protection plan<br />

comments until water supply line installation is complete.<br />

" DDI informed that water supply lines will not all be in place before start up. Discussion of not<br />

tying directly to a hydrant. There will be no direct filling of trucks until an alternative to hard tieins<br />

is in place. WCH will be issuing a CN revising the specification to use only a water fill<br />

stations for water trucks. J-stand is erected and is working on making it fuinctional.<br />

* PRC Deputy Fire Marshall has requested sketch of water system configuration that will be<br />

constructed. DDI to provide. The excavation permit and non-emergency hydrant tie-in permit<br />

approvals are with the CHPRC 100-K Fire Protection Engineer pending their approval of this<br />

system. Additional request has been made for CAD drawings of this configuration by the Fire<br />

Protection Engineer. WCH will develop a CAD drawing from the info that DDI has provided.<br />

Waiting on FPE authorization.<br />

" Discussed load-out start-up behind excavation and sorting. DDI request to revise PSR to have<br />

container loading and handling as a post-start for the dry runs. Dry-runs have been completed<br />

and loadout authorized.<br />

" DDI to have offsite vendor to train site personnel to inspect scaffolding. Currently DDI only has<br />

one (1) competent person. DDI waiting on training resource to get additional persons trained.<br />

" DDI plans to add a water truck (third) and driver as the weather turns drier. The second water<br />

truck will be on site later this week.<br />

* WCII to provide container load out sheets. DDI to include previous day's load counts with daily<br />

report. Daily provision of DDI daily reports continues to need improvement.<br />

I11. PROJECT DESIGN DRAWINGS<br />

* Electrical drawings are in process. Diesel storage tank electrical designs and trailer site electrical<br />

as well as as-built drawings. DDI will be re-submitting drawings which will incorporate WCH<br />

comments.<br />

* DDI to resubmit Traffic Control Plans which will incorporate comments from WCH. DDI to<br />

submit 12/1/09.<br />

IV.<br />

UPDATED ROLLING 3-4 WEEK LOOK AHEAD SCHEDULE<br />

* See attached.<br />

V. WEEKLY PRODUCTION TABLE<br />

0 None.<br />

VI.<br />

VII.<br />

MANPOWER<br />

" See attached.<br />

" Mr. McQueary plans to be transitioned out by 12/22/09 if possible.<br />

* WCH waiting for the requested DDI site superintendent and project manager transition plans.<br />

EQUIPMENT<br />

* See attached.