Progress Review Meeting<br />

Page 5<br />

comments and will resubmit. DDI to submit by 1/28/2010. WCH has received, in preliminary<br />

review, will return this week. WCH returned to DDI, status 2, with comments. DDI will be<br />

doing a walkdown with Mr. Teachout to incorporate comments and will resubmit drawings for<br />

approval. DDI to check on status. DDI waiting on North Point. DDI still waiting on North<br />

Point. They have exceeded the 30-day expected response to a returned submittal. DDI to follow<br />

up with North Point again this week. No update, still with DDI (4/20). No update (4/27).<br />

*WCH requests as-built drawings of the energized water system.<br />

XIII. CHANGE NOTICES/STATUS/CHANGE ORDERS<br />

* See attached.<br />

XIV.<br />

XV.<br />

XVI.<br />

CORRESPONDENCE<br />

* Letter from DDI: Acknowledgement of Change Notice 025<br />

* Weekly Progress Review Meeting Minutes of 4/20/2010<br />

IN VOICE AND PAYMENT STATUS<br />

* April month end was April 22, 2010.<br />

OTHER COMMENTS/NEW ACTION ITEMS<br />

* Discussed issue of inaccurate scale weights. DDI has instructed Watts to install a new scale. The<br />

scale is part of the contract between Watts and DDI. WCH asks that the work be completed no<br />

later than the end of May with work to be completed on weekends so not to take away from<br />

production.<br />

* An informal meeting with WCH, DDI and ESHI will be scheduled to discuss start and stop times<br />

in the HRA.<br />

" DDI is reminded that Daily Reports are to be submitted to WCH the following day. If the person<br />

who normally completes these is out, a back up needs to be identified and trained.<br />

" There is an issue with not having Tyvec booties for some site personnel when they are required to<br />

enter the trenches for sampling. DDI commits to getting some on site immediately.<br />

* DDI needs to survey signage used in the CRZ postings. Currently some signs state "Caution"<br />

while others on the same rope state "Danger". The correct warning level for the CRZ is<br />

"Caution". DDI will address this.<br />

" DDI asked that WCH clarify the definition of anomalies. There seems to be some confusion on<br />

what actually constitutes an anomaly.<br />