17.12.2013 Views

FOI_2011-00646_Enclosure - Hanford Site

FOI_2011-00646_Enclosure - Hanford Site

FOI_2011-00646_Enclosure - Hanford Site

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Progress Review Meeting<br />

Page 3<br />

and then contract with Northpoint to complete the remainder of the ladder installation. DDI to<br />

complete fall prevention JHA and make sure that work package is discussed and clear to all<br />

involved. DDI discussing a "flip-plate" to be used to stick check levels in the tank from the top<br />

of the ladder. DDI needs to check that modifications made to the tank are in compliance with the<br />

manufacturer's specs. Ladder to be installed today (3/23/2010). Ladder installation delayed<br />

because the bolts where too large for the holes. New DDI PM will be revisiting this matter<br />

(4/20). Watts is looking into the costs associated with placing scaffolding around the tank.<br />

Another alternative is to bring a man-lift to the site (4/27). No update. (5/4) No update. (5/11)<br />

No update. (5/18) DDI has re-evaluated and determined no reconfigurations will be made to the<br />

tank. (5/25)<br />

* Discussed issue of inaccurate scale weights. DDI has instructed Watts to install a new scale. The<br />

scale is part of the contract between Watts and DDI. WCH asks that the work be completed no<br />

later than the end of May with work to be completed on weekends so not to take away from<br />

production. (5/4) No change. WCH discussed the need to coordinate long lead time for<br />

scheduling teamster to remove from site the scale being replaced. (5/11) No change. DDI subtier<br />

(Watts) has to plans at this time to replace scale. (5/18) It is questionable if scale is issuing<br />

consistent weight that is reliable.<br />

* DDI is reminded that Daily Reports are to be submitted to WCH the following day. If the person<br />

who normally completes these is out, a back up needs to be identified and trained. This continues<br />

to be a challenge. (4/27) WCH noted that this is the DDI PM's responsibility. As this continues<br />

to be an issue, DDI is putting themselves in a deficient position. (5/11) No change. (5/18)<br />

a<br />

DDI asked that WCI I clarify thc dcfinition of anomalies. There seems to be some confusion on<br />

DDI's part what actually constitutes an anomaly. No update. A meeting will be held to discuss<br />

this today (5/4). DDI requested an additional meeting to discuss delays related to anomalies.<br />

This is scheduled for 5/12/20 10 at 1:00. (5/11) Meeting rescheduled for Thursday, 5/20/2010.<br />

(5/18) Meeting held 5/25/20 10.<br />

0 DDI has not received any information on the Trench I camera specs or equipment specs for the<br />

400 excavator. They will follow up with the vendor. (5/11) Some specs have been received, but<br />

more are needed. Confer with D. Teachout for specifics. (5/18) WCH is in development of<br />

change notice for Trench I work.<br />

* There are several safety items that need DDI attention from last week's safety walkdown.<br />

(Cover/Storage for the breathing air bottles, cord trees for the fans used in the field, fixative hose<br />

at the tent, and move the batteries charging in the conex.) (5/11) There has been no progress<br />

made in making these corrections. (5/18) "S"-hook installed for electrical cords, fixative hose has<br />

been corrected, and batteries are no longer being charged in Conex. No progress on cover and<br />

storage for breathing air bottles. (5/25)<br />

0 DDI to submit REA for mandatory Beryllium training held on 5/17/20 10. This will be part of the<br />

delay discussion meeting to be held on Thursday 5/20/2010. DDI will be submitting and REA for<br />

All-Hand meeting and Safety Expo.<br />

* Discussed Incidental Welding procedure. Surveillance performed, identified necessary changes<br />

to be made for clarifications. (5/18) No update. (5/2 5)<br />

* WCH expressed concerns about delays in completion of subcontract administrative duties and<br />

paperwork. WCH suggests that DDI take a look at how to best resolve this issue. (5/18)<br />

11I. PROJECT DESIGN DRAWINGS<br />

*DDI still needs to submit for WCH review as-builts for electrical as well as the energized water<br />

line. (5111) No change. (5/18) No change. (5/25)

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!