Progress Review Meeting<br />

Page 3<br />

manufacturer's specs. Ladder to be installed today (3/23/2010). Ladder installation delayed<br />

because the bolts where too large for the holes. New DDI PM will be revisiting this matter<br />

(4/20). Watts is looking into the costs associated with placing scaffolding around the tank.<br />

Another alternative is to bring a man-lift to the site (4/27). No update. (5/4) No update. (5/11)<br />

* WCH has three confirmatory sampling sites what will require DDI equipment support. More<br />

information will be provided soon. WCH pushing for an April timeframe to perform this work.<br />

A walkdown of one of the sites will be occurring today. WCH will schedule a discussion for next<br />

week to discuss the excavation of the two or 3 sites that are included in the current contract.<br />

Potholing to commence 5/17/2010 when DDI's new sampler has completed her training. A<br />

meeting will be held prior to the sampling to ensure that DDI has everything on hand to support<br />

the excavation activities for confirmatory sampling at 600-29 (4/27). On track to have sampler<br />

training in place by 5/17/2010 (5/4). Pot holing to begin 5/18/2010. (5/11)<br />

* Discussed issue of inaccurate scale weights. DDI has instructed Watts to install a new scale. The<br />

scale is part of the contract between Watts and DDI. WCH asks that the work be completed no<br />

later than the end of May with work to be completed on weekends so not to take away from<br />

production. (5/4) No change. WCT discussed the need to coordinate long lead time for<br />

scheduling teamster to remove from site the scale being replaced. (5/11)<br />

* An informal meeting with WCH, DDI and ESHI will be scheduled to discuss start and stop times<br />

in the HRA. (4/27) This schedule is to be implemented by Monday, 5/17/20 10.<br />

* DDI is reminded that Daily Reports are to be submitted to WCH the following day. If the person<br />

who normally completes these is out, a back up needs to be identified and trained. This continues<br />

to be a challenge. (4/27) WCH noted that this is the DDI PM's responsibility. As this continues<br />

to be an issue, DDI is putting themselves in a deficient position. (5/11)<br />

* There is an issue with not having Tyvec booties for some site personnel when they are required to<br />

enter the trenches for sampling. DDI commits to getting some on site immediately. DDI has<br />

procured, will provide arrival date. (5/4) Tyvec booties have been received, but DDI is still<br />

waiting on rubber overshoes. (5/11)<br />

" DDI asked that WCH clarify the definition of anomalies. There seems to be some confusion on<br />

DDI's part what actually constitutes an anomaly. No update. A meeting will be held to discuss<br />

this today (5/4). DDI requested an additional meeting to discuss delays related to anomalies.<br />

This is scheduled for 5/12/2010 at 1:00. (5/11)<br />

* Getting rock truck back on site in order to complete safety bench in trench L is a priority. (5/4)<br />

This is not an issue; the truck is on-site at the 1 00-K project next door and can be made available<br />

as needed. (5/11)<br />

III.<br />

IV.<br />

PROJECT DESIGN DRAWINGS<br />

*DDI still needs to submit for WCH review as-builts for electrical as well as the energized water<br />

line.<br />

UPDATED ROLLING 3-4 WEEK LOOK AHEAD SCHEDULE<br />

* See attached.<br />

V. WEEKLY PRODUCTION TABLE<br />

* See attached.<br />

VI.<br />

MANPOWER<br />

*DDI is struggling to find another CIH to fill the CIH Key personnel position.<br />

0 Bill McKee (CIH) is no longer on staff. DDI is pursuing another CIH candidate at this time