Progress Review Meeting<br />

Page 2<br />

review. To be scheduled for next week. (8/24) DDI to provide a letter response. Meeting<br />

rescheduled for Wednesday 9/1. (8/3 1) Meeting held last week, scheduling will continue as<br />

needed. (9/7) DDI would like to schedule this to follow the 9/27 1:00 meeting. (9/22) Meeting<br />

rescheduled for Monday at 1:00 p.m. (9/28) Delay impacts meeting scheduled for 10/6/10 at<br />

1:00. (10/5) Delay impacts meeting to be rescheduled, time TBD. (10/12) DDI has completed<br />

review and would like to meet again to put this issue to rest. Meeting will be scheduled as soon<br />

as possible. (10/26) Meeting rescheduled for today at 1:00 to discuss the last couple weeks. A<br />

meeting to discuss impacts TBD. (11/2) Delay status meeting today at 1:00. (11/9) WCH and<br />

DDI met on 11/15/2010 and will continue these discussions. (11/16) WCH would like to have<br />

complete agreement on delays so DDI is in a position to submit request for delays past 45 days.<br />

The weekly meetings will resume beginning Thursday, 12/2. (11/30) Currently, delays have been<br />

discussed through the end of November. DDI to respond to WCH letter regarding delays.<br />

Moving forward, DDI will follow the equipment and manpower process as lined out in Exhibit B<br />

from this date forward. (12/7) WCH is requesting that DDI provide a letter of agreement on the<br />

45-day of scheduled delays. In return, WCH will provide to DDI a letter agreeing to a calculated<br />

method versus TIA for delays. November 30th was the last day of the 45-day of delays. (12/14)<br />

WCH to respond to 12/15/10 DDI delays letter, concurrent to meeting 45 days of Exhibit B<br />

delays as of 11/30/10. This letter will include explanation of how the delay days were<br />

determined/calculated. (12/28)<br />

" Stainless steel acid overpack decontamination needs to be completed. (10/12) This has not yet<br />

been done. Drums are currently contained in the anomaly staging area. (10/26) Characterization<br />

plan development is in process. The drums are in an exclusion zone due to the contamination on<br />

the outside of the drums. (11/2) No change. (11/9) WCH is developing a characterization plan.<br />

(11/16) No update. (11/30) Characterization plan is with WCH Engineering for review. (12/7)<br />

No update. (12/14) Characterization plan is at the planning for evaluation. (12/28)<br />

" WCH asks if there is an "all-call" option available on the radios which, when triggered, makes an<br />

announcement over all of the radio channels. The option is not the scan function that<br />

automatically changes channels, but one that issues announcements simultaneously over all<br />

channels. WCH requests that DDI look into this and if available check into the costs of<br />

purchasing several for the project. (10/26) DDI is still researching options. (11/2) DDI has<br />

received a quote for this function and will look into scheduling to have the radios programmed<br />

over the Thanksgiving holiday. WCH to provide change notice for DDI to proceed with this.<br />

(11/9) DDI has plans to take all the radios off site on 11/23 for reprogramming over the holiday<br />

period. (11/16) Reprogramming of the radios has been delayed until mid-December due to the<br />

unavailability of the vendor. (11/30) WCH has 30 radios. (12/7) Plan to reprogram radios has<br />

been pushed to either the Christmas or New Year break in work. All radios will be<br />

reprogrammed to receive the announcement, and three radios will have the broadcast function. A<br />

total of sixty radios in all. DDI requests a change notice for the cost of the reprogramming.<br />

(12/14) DDI has had all radios reprogrammed and redistributed. DDI to provide CN proposal by<br />

COB this week. (12/28)<br />

" WCH will follow-up on procurement of odor control materials for potential use in Trench K.<br />

(11/16) WCH 11- suggested using a charcoal substance to mix with the soil rather than using the<br />

proposed odor control chemical. No update past this recommendation from I1H. WCH to followup<br />

on this. (11/30) No viable engineering controls are available. On the next available Friday,<br />

the crew will do a thorough resort and mix of Trench K. (12/7) Re-sort successfully performed on<br />

12/10. WCH has some work package and management requirements that need to be satisfied<br />

before work can begin again in Trench K. (12/14) Secondary Sort of odorous materials to begin<br />

Monday, 1/3. (12/28)