Progress Review Meeting<br />

Page 8<br />

XIV.<br />

XV.<br />

XVI.<br />

CORRESPONDENCE (since last meeting)<br />

* Transmittal from DDI: Acceptance of CN 025 Rev. 1<br />

" Weekly Progress Review Meeting Minutes of 7/27/2010<br />

INVOICE AND PAYMENT STATUS<br />

* Discussion of completion incentive by trench. Per the contract DDI has the potential for partial<br />

release of retention. For Trenches D, E, P and G one-half of the retainage may be released when<br />

completed. A topographical survey will be required.<br />

* DDI to submit invoice this week for July work.<br />

o As energized as-builts have not yet been received, WCH anticipates additional 15%<br />

withholding from July payment.<br />

OTHER COMMENTS/NEW ACTION ITEMS<br />

0 Monthly Air Quality Data Summary Records have not been seen/reviewed by Dan Saueressig<br />

(WCH EPL) since November.<br />

* WCH asked how DDI is tracking BCL material. No measurement/tracking of BCL material has<br />

been provided to WCH.<br />

o DDI indicated a survey will be completed to measure quantity when the stockpile is<br />

completed.<br />

& Delay meeting will be held 7/27 at 1:00.<br />

Attachment(s): As noted above.