17.12.2013 Views

FOI_2011-00646_Enclosure - Hanford Site

FOI_2011-00646_Enclosure - Hanford Site

FOI_2011-00646_Enclosure - Hanford Site

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Progress Review Meeting<br />

Page 3<br />

" Planned dry run for Trench I to begin 11/29. (11/16) Start pushed out due to weather. (11/30)<br />

Need to pinpoint starting dates for dry runs now that equipment is located in the HRA. WCH to<br />

review the PSR to determine what will be evaluated for readiness from the dry run. (12/7) A dry<br />

run checklist will be developed after the holidays for the 400 excavator. (12/14) Dry run in<br />

Trench A to begin 1/3/11 as planned. (12/28) Dry runs have been moved to 1/6. (1/4) Dry runs<br />

utilizing Trench A were performed on 1/6-11, WCH RE currently working on video connection<br />

troubleshooting. (1/12)<br />

" Trench I work package training to begin Tuesday 1/4/11 after the POD. (1/4) Completed 1/5/11.<br />

(1/12)<br />

" Trench I RWP and BWP training to begin Wednesday 1/5/11 after the POD. (1/4) The RWP was<br />

briefed with the crew on 1/6/11. (1/12)<br />

" John Heard will be leaving the project and WCH. Doug Ordal will be taking over as Subcontract<br />

Specialist for the project. (12/28) Doug Ordal introduced to key project personnel. (1/4) WCH<br />

will provide a letter to DDI announcing the appointment of Doug to the project. (1/12)<br />

* Discussed requirement for discussing work to be performed prior to performance (tailgates, work<br />

authorization, necessary oversight, etc.) (12/28) DDI suggested that the Plan-of-Tomorrow<br />

meeting be more formalized. POT will become a scheduled daily meeting at 1530 hours each<br />

day. (1/4) The more formalized POT appears to be working well. (1/12)<br />

Ill.<br />

IV.<br />

PROJECT DESIGN DRAWINGS<br />

* None.<br />

UPDATED ROLLING 3-4 WEEK LOOK AHEAD SCHEDULE<br />

* No change from last week.<br />

* Trench I work package training scheduled for 1/5/11 after the POD. (1/4) Crew briefing<br />

performed 1/5/11. (1/12)<br />

* Trench I RWP and BWP training scheduled for Thursday 1/6/11 after the POD. (1/4) Crew<br />

received briefing on the Trench I RWP on 1/6/11. (1/12)<br />

* PSR in final review and plans are for WCH to have it available to be signed off Monday or<br />

Tuesday of next week. (1/4) PSR sign off has been rescheduled for Monday, 1/17/11. (1/12)<br />

o<br />

o<br />

After PSR is signed off, cone penetrometers and lids will be pulled.<br />

Block wall will be completed. (1/4) The first layer of the block wall has been completed.<br />

Once the cone penetrometers and lids are removed, the remainder of the wall will be<br />

constructed. (1/12)<br />

V. WEEKLY PRODUCTION TABLE<br />

" No intrusive work can be started relative to Trench I until the PSR has been approved and signed<br />

off by WCH management.<br />

" None.<br />

VI.<br />

VII.<br />

MANPOWER<br />

* None provided. Verbal confirmation of new and resigned subcontractor employees mentioned.<br />

(1/12)<br />

EQUIPMENT<br />

0 No change from last week.<br />

VIII. WORK PACKAGE NEEDS IN ORDER OF PRIORITY AS SET BY DDI

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!