Progress Review Meeting<br />

Page 4<br />

111. PROJECT DESIGN DRAWINGS<br />

*WCH return electrical and traffic control drawings to DDI, status 2. DDI will be resubmitting<br />

soon incorporating the WCH comments. DDI to submit this week. Drawings are with North<br />

Point for revision and will be resubmitted upon their return. DDI is well beyond the 30-day<br />

resubmission for updated drawings. WCH will be issuing an SDR regarding this issue. DDI has<br />

indicated they are working on a deficiency letter which will be submitted to Watts for this and<br />

several other deficiencies.<br />

o Electrical drawings are a priority as CHPRC will be making some revisions to them for<br />

some additional air monitoring stations on the 118-K electrical service. No update (4/20).<br />

IV.<br />

UPDATED ROLLING 3-4 WEEK LOOK AHEAD SCHEDULE<br />

* See attached.<br />

V. WEEKLY PRODUCTION TABLE<br />

* See attached.<br />

VI.<br />

VII.<br />

MANPOWER<br />

*DDI has extended an offer to a CIH candidate. The candidate has accepted the offer of <strong>Site</strong><br />

Safety and Health Officer. DDI is struggling to find a CIH to fill the CIII Key personnel position.<br />

EQUIPMENT<br />

" WCH will be discussing with DDI the possible use of the JD 225 for the confirmatory sampling.<br />

" The Kenworth haul trucks are on hold for use with 25-ton cans until final certification data is<br />

provided. Submittal for certification was returned status 3.<br />

" DDI has instructed Watts to continue installation of the soil bonding agent injection system that<br />

will tie into the water system.<br />

" Equipment to be identified for the Trench I Silo remediation.<br />

VIII. WORK PACKAGE NEEDS IN ORDER OF PRIORITY AS SET BY DDI<br />

*Clarification of distance to remain from a non-bermed edge of a trench. Planners are working on<br />

this clarification.<br />

IX<br />

MATERIAL<br />

0 DDI to address getting calcium chloride on site before current supply of fixative runs out.<br />

X. QUALITY<br />

*Construction, Drawings and Procedures Surveillance to be completed this week (DDI QA Manual<br />

Section 5).<br />

XI.<br />

XII.<br />

REQUESTS FOR INFORMATION<br />

* DDI will be issuing an RFI for the scheduler position, duties and WCH expectations.<br />

* DDI will be issuing an REI to further discuss the independent CIH position and other possible<br />

options.<br />

TECHNICAL DATA SUBMITTALS/STATUS<br />

" See attached.<br />

* Electrical Drawings for electrical tie-ins, as-builts and diesel tank electrical design have been<br />

submitted to WCH. Review and comments to be returned to RDC today. DDI incorporating