Progress Review Meeting<br />

Page 3<br />

with new date TBD. (6/22) No change. (6/29) No change. (7/6) This will be tentatively<br />

rescheduled for Friday, July 30 pending support availability. (7/14) DDI expressed beryllium<br />

concerns for this activity. WCH has determined this site to be beryllium free, but this is being reevaluated<br />

by WCH 111. (7/20) A re-evaluation determined the area to be beryllium free. The<br />

"Beryllium Free Facility" form has been signed off by WCH 1H. WCH will evaluate if there is<br />

support available for working on 7/30. (7/27) Work did not occur on 7/30, DDI to request<br />

working Friday, 8/20 when their sampler is available to support this work. (8/3) No update.<br />

(8/10) WCH commits to supporting confirmatory sampling and limited CTA maintenance<br />

activities on 8/20. WCH will provide OT approval today. (8/17)<br />

" Prior to moving the truck scale with the non-conforming lifting eye, a lift plan will be developed.<br />

(8/3) This item will remain in these minutes until demobilization as a reminder. (8/10)<br />

" Discussed future start-up plans for Trench N. DDI to present plan for Trench N for WCH<br />

concurrence before the start of intrusive activities. (6/22) No change. (7/6) DDI to schedule a<br />

meeting Monday 7/19 with pertinent DDI and WCH personnel to discuss plan for Trench N.<br />

(7/14) This meeting has been delayed until the week of 7/26 to ensure key DDI personnel are<br />

able to attend. (7/20) Meeting to be scheduled for 7/29 at 1:00. (7/27) DDI is developing work<br />

plan as discussed in meeting. A follow up meeting scheduled for Thursday afternoon at 1:00.<br />

Discussed the status of plans for handling and disposition of known large canisters in Trench K,<br />

DDI to provide details. (6/29) No update. (7/6) This will be included in the discussion to be<br />

scheduled on Monday afternoon, 7/19. (7/14) This meeting has been delayed until the week of<br />

7/26 so key DDI personnel are able to attend. (7/20) This meeting will be rescheduled to the<br />

same time as the Trench N discussion. (7/27) Canisters will be loaded out into single use<br />

containers. This will be included as part of the discussion in Thursday's meeting. (8/3) Meeting<br />

scheduled last week was delayed. Meeting rescheduled to follow delay meeting this afternoon if<br />

the key personnel are available. (8/10) Meeting to be rescheduled to 1:00 Wednesday 8/18.<br />

(8/17)<br />

" DDI is scheduling a 25-ton certification scale test for Kenworth trucks on Tuesday, June 29 at<br />

10:00. A WCH engineer will participate in witnessing the test. (6/22) Test rescheduled to 6/30.<br />

DDI working to obtain information from G & H for hoist modifications. (6/29) Test, as<br />

performed, was not successful. DDI is making arrangements for another test, tentatively<br />

scheduled for 7/12/2010. (7/6) A second test was performed without success. DDI is submitting<br />

certifications today for four (4) of the shuttle trucks. (7/14) These include the 22-ton shuttle<br />

trucks. (7/14) DDI has submitted certs, WCH has not received. DDI is planning on bringing an<br />

additional 25-ton truck to the project. (7/20) One Kenworth truck will be removed from the site,<br />

to be replaced by a 25T Peterbilt truck. (7/27) WCH has received submittals and is in review.<br />

Truck will be on-site by the end of this week. (8/3) DDI to submit cert for new Peterbuilt truck<br />

by end of the day. (8/10) All certs have been approved by WCH and are being returned status 1.<br />

(8/17)<br />

" On 7/8/2010 DDI submitted a letter addressing delays. WCH commits to providing a response<br />

when the STR returns from vacation. This will be a priority upon his return. (7/20) WCH will<br />

have this to DDI by the end of the week. (8/3) WCH has prepared a response letter and it will be<br />

given to DDI today. (8/10) Discussion of delays and WCH's letter in response to DDI's request.<br />

Further discussion tabled to another meeting. (8/17)<br />

* WCH asked how DDI is tracking BCL material. No measurement/tracking of BCL material has<br />

been provided to WCH. (7/27) DDI states they are tracking loader buckets and CAT truck loads<br />

on a daily report. They will confirm if it is included in the daily report being provided to WCH.<br />

(8/10)<br />

o DDI indicates this is being tracked. WCH would like to review data; DDI will include in