Progress Review Meeting<br />

Page 2<br />

work on water line on an off shift work day, pushing for Friday 2/19/20 10. Excavation permit is<br />

complete. Discussed that 1 00-K water will be shut-off this weekend. Friday work is pending.<br />

Further discussed backflow preventer versus air-gap installation requirements. DDI is pursuing<br />

additional changes to the water system tie-in. WCH met with CHPRC again on 2/22/2010. DDI<br />

to complete system construction while new permits are pending. Decision has been made to<br />

utilize the existing permits in place. DDI will begin to get materials on site to support installation<br />

of water tie-in to support installation date of Friday, 3/19/2010. Work inside the fence next door<br />

needs to be complete by the end of the weekend of the 1 9 th so not to disrupt their work. DDI<br />

indicated system should be operational the week of March 22. DDI waiting on materials, flow<br />

restrictors, tanks, calcium chloride. Underground installations completed in the 100-K area. DDI<br />

does not yet have parts on-site to complete the above ground installations to complete the tie-ins.<br />

DDI to provide information/details for additional flow requests. DDI to prepare as-built<br />

information prior to energizing system. High tank is in place and operational. DDI is having<br />

some issues with float valve that they are continuing to work through. Getting this system<br />

operational inside the burial ground needs to be a priority. DDI is working through a request by<br />

Watts for additional GPM. DDI is considering bringing in another sub to complete the water<br />

system project (4/20). DDI is evaluating a recalculation of water system requirements from Watts<br />

and will forward to WCH after review. Watts has been instructed by DDI to continue installation<br />

of the stabilization injection system related to the water system. WCH requests a P&ID of the<br />

water system (4/27).<br />

" Discussion of waste oil uses and testing of same if oil is taken off site. Will discuss fujrther with<br />

environmental regarding Watts' re-use of waste oil. WCH is investigating from an environental<br />

perspective. DDI to supersede the SPCC with an OMP. WCH has evaluated waste oil for<br />

heaters. DDI to provide a designation of non-regulated and/or specification on used oil that<br />

qualifies to burn prior to removal of any waste oil from the site. When DDI has submitted OMP,<br />

Environmental will get WCH concurrence. DDI plans to submit by 1/27/2010. DDI requesting<br />

assistance/support with designations. WCH in review of the OMP, WCH will provide support to<br />

DDI with the required designations for waste oil burning. DDI to submit revised OMP this week.<br />

DDI is working with WCH EPL on clarifications. WCH EPL to observe Watts's oil burning<br />

facility on 3/18/2010. DDI will submit OMP after that date. OMP waiting on ARES revision to<br />

drawings, then DDI will submit. Drawings should be available for pickup by DDI this week then<br />

the OMP will be submitted. No update (4/20). DDI is working on final review of this submittal<br />

and will submit by 5/11/2010 (4/27).<br />

" DDI to provide a plan to access the top of the diesel fuel storage tank. DDI confirmed ladder is<br />

on site. Will be meeting with WCH Safety about use and training requirements prior to<br />

developing and implementing a plan for utilization. DDI plans to construct scaffolding with<br />

handrails to access top of tank. WCH will be issuing a new scaffolding procedure soon and will<br />

incorporate any potential changes or impacts to the subcontractor. DDI will be installing a ladder<br />

and tie-off point next week. WCH will need to have the tie-off point inspected by a qualified<br />

person prior to use. DDI will install ladder bolts from the ground for the first two or three rungs<br />

and then contract with Northpoint to complete the remainder of the ladder installation. DDI to<br />

complete fall prevention THA and make sure that work package is discussed and clear to all<br />

involved. DDI discussing a "flip-plate" to be used to stick check levels in the tank from the top<br />

of the ladder. DDI needs to check that modifications made to the tank are in compliance with the<br />

manufacturer's specs. Ladder to be installed today (3/23/20 10). Ladder installation delayed<br />

because the bolts where too large for the holes. New DDI PM will be revisiting this matter<br />

(4/20). Watts is looking into the costs associated with placing scaffolding around the tank.<br />

Another alternative is to bring a man-lift to the site (4/27).