Progress Review Meeting<br />

Page 5<br />

XII.<br />

XIII.<br />

XIV.<br />

XV.<br />

XVI.<br />

TECHNICAL DATA SUBMITTALS/STATUS<br />

* See attached.<br />

* Electrical Drawings for electrical tie-ins, as-builts and diesel tank electrical design have been<br />

submitted to WCH. Review and comments to be returned to RDC today. DDI incorporating<br />

comments and will resubmit. DDI to submit by 1/28/2010. WCH has received, in preliminary<br />

review, will return this week. WCH returned to DDI, status 2, with comments. DDI will be<br />

doing a walkdown with Mr. Teachout to incorporate comments and will resubmit drawings for<br />

approval. DDI to check on status. DDI waiting on North Point. DDI still waiting on North<br />

Point. They have exceeded the 30-day expected response to a returned submittal. DDI to follow<br />

up with North Point again this week. No update, still with DDI (4/20). No update (4/27). No<br />

update (5/4).<br />

* WCH requests as-built drawings of the energized water system. No update (5/4).<br />

CHANGE NOTICES/STATUS/CHANGE ORDERS<br />

0 See attached.<br />

CORRESPONDENCE<br />

* Weekly Progress Review Meeting Minutes of 4/27/2010<br />

IN VOICE AND PAYMENT STATUS<br />

* DDI will be submitting April invoice soon.<br />

OTHER COMMENTS/NEW ACTION ITEMS<br />

* Getting rock truck back on site in order to complete safety bench in trench L is a priority.<br />

* WCH needs documentation of safety recall repairs that has been completed on the two leased<br />

shuttle trucks.<br />

Attachment(s): As noted above.