Progress Review Meeting<br />

Page 2<br />

tank. Permits scheduled to be complete by 1/14/2010. Still waiting on permits from CHPRC.<br />

WCH following up. Hydrant permnit is in hand, waiting for excavation permit. Plan to perform<br />

work on water line on an off shift work day, pushing for Friday 2/19/20 10. Excavation permit is<br />

complete. Discussed that 100-K water will be shut-off this weekend. Friday work is pending.<br />

Further discussed backflow preventer versus air-gap installation requirements. DDI is pursuing<br />

additional changes to the water system tie-in. WCH met with CHPRC again on 2/22/2010. DDI<br />

to complete system construction while new permits are pending. Decision has been made to<br />

utilize the existing permits in place. DDI will begin to get materials on site to support installation<br />

of water tie-in to support installation date of Friday, 3/19/20 10. Work inside the fence next door<br />

needs to be complete by the end of the weekend of the 19'h so not to disrupt their work. DDI<br />

indicated system should be operational the week of March 22.<br />

* Discussion of waste oil uses and testing of same if oil is taken off site. Will discuss further with<br />

environmental regarding Watts' re-use of waste oil. WCH is investigating from an environmental<br />

perspective. DDI to supersede the SPCC with an OMP. WCH has evaluated waste oil for<br />

heaters. DDI to provide a designation of non-regulated and/or specification on used oil that<br />

qualifies to burn prior to removal of any waste oil from the site. When DDI has submitted OMP,<br />

Environmental will get WCH concurrence. DDI plans to submit by 1/27/20 10. DDI requesting<br />

assistance/support with designations. WCH in review of the OMP, WCH will provide support to<br />

DDI with the required designations for waste oil burning. DDI to submit revised OMP this week.<br />

DDI is working with WCH EPL on clarifications.<br />

* WCH requests a site absences coverage plan. WCH to give DDI comments. DDI plans to submit<br />

this by 1/26/2010. WCH to provide review and comments. DDI to resubmit incorporating WCH<br />

feedback. DDI will resubmit this week. WCH has returned with comments, status 2.<br />

" DDI to provide a plan to access the top of the diesel fuel storage tank. DDI confirmed ladder is<br />

on site. Will be meeting with WCH Safety about use and training requirements prior to<br />

developing and implementing a plan for utilization. DDI plans to construct scaffolding with<br />

handrails to access top of tank. WCH will be issuing a new scaffolding procedure soon and will<br />

incorporate any potential changes or impacts to the subcontractor. DDI will be installing a ladder<br />

and tie-off point next week. WCH will need to have the tie-off point inspected by a qualified<br />

person prior to use. DDI will install ladder bolts from the ground for the first two or three rungs<br />

and then contract with Northpoint to complete the remainder of the ladder installation.<br />

* DDI will be providing calcium chloride for the water system when it is operational. Before<br />

Trench K is opened up, DDI to have calcium chloride on site for dust control. DDI to look into<br />

utilizing Dust Bond in trenches K, N, 0 and 1. DDI to provide mixture ratios for WCH profile.<br />

WCH is looking into the availability of having Dust Bond totes on site for use with dust control.<br />

* DDI evaluating a location for truck washing. This will be coordinated with the WCH EPL.<br />

" DDI asked if the issue regarding a scaffolding competent person has been resolved. WCH Safety<br />

Rep to follow up on any additional approvals that are required. Per WCH Safety Rep, all training<br />

requirement for scaffold use have been met.<br />

" Discussed pre-excavation survey point limitations. DDI to have surveyors out to the site to<br />

review to ensure excavation limits are captured in the Pre-Excavation surveys. DDI will schedule<br />

the surveyors back on site to survey Trenches J, L, D, E, P and the north end of C.<br />

" Trench "I" planning and discussions are underway. DDI has not yet received any feedback from<br />

Rowand regarding bucket dimensions, spec sheet, cameras, etc. DDI to provide this information<br />

by Monday, 3/18/2010. The Jewel rep was on site this week and is going to provide additional<br />

information to answer the questions raised. DDI needs to provide a large number of ecology<br />

blocks for use in Trench 1. These need to be rate, in new or very good shape, and have a picking<br />

eye.