Progress Review Meeting<br />

Page 3<br />

DDI plans to submit the OMP next week. (5/18) Submission of OMP pushed out to 6/3/2010.<br />

(5/25) No change. (6/1) DDI is still working on OMP submittal. (6/8) No change, DDI to<br />

submit by 6/24/10. (6/15) DDI is on schedule to meet 6/24 submission. (6/22) WCH has<br />

received OMP and is in review. (6/29) WCH is still reviewing. (7/6)<br />

* Discussed Incidental Welding procedure. Surveillance performed, identified necessary changes<br />

to be made for clarifications. (5/18) No update. (5/25) DDI to revise this week. (6/1) DDI to<br />

submit by 6/10/2010. (6/8) DDI commits to submitting no later than 6/24/10. (6/15) DDI on<br />

schedule for submission by 6/24. (6/22) WCH has received and is in review. (6/29) WCH has<br />

returned to DDI status 2. (7/6)<br />

" DDI and WCH are planning to perform confirmatory sampling on one test pit and two trenches<br />

for 100-K-2 on the day the scale is being replaced - June 18. (6/8) This activity was rescheduled<br />

with new date TBD. (6/22) No change. (6/29) No change. (7/6)<br />

" It appears the potable water holding tank in the shower trailer is just bolted into the wall. DDI to<br />

take a look at this configuration for safety considerations. (6/1) DDI feels that current<br />

configuration is adequate. DDI to revisit issue with WCH STR. (6/8) No change. (6/15) No<br />

change. (6/22) No change. (6/29) No change. (7/6)<br />

" DDI to develop NCR for the suspect/modified lift points on the new truck scale. (6/22) NCR has<br />

been implemented and DDI is developing a documented path forward to address the NCR. (6/29)<br />

* DDI to submit REA for 100-K-2 confirmatory sampling. (6/22) DDI to submit by 6/30. (6/29)<br />

No change. (7/6)<br />

" Discussed future start-up plans for Trench N. DDI to present plan for Trench N for WCH<br />

concurrence before the start of intrusive activities. (6/22) No change. (7/6)<br />

" DDI is scheduling a 25-ton certification scale test for Kenworth trucks on Tuesday, June 29 at<br />

10:00. A WCH engineer will participate in witnessing the test. (6/22) Test rescheduled to 6/30.<br />

DDI working to obtain information from G & H for hoist modifications. (6/29) Test, as<br />

performed, was not successful. DDI is making arrangements for another test, tentatively<br />

scheduled for 7/12/2010. (7/6)<br />

* Discussed requirements for daily reports. Daily reports are to be provided to WCH by noon the<br />

following business day. (6/22) DDI commits to making this happen. (6/29)<br />

" Discussed the status of plans for handling and disposition of known large canisters in Trench K,<br />

DDI to provide details. (6/29) No update. (7/6)<br />

* Discussed Beryllium controls and medical surveillance requirements for Trench I remediation.<br />

(5/25) Medical screen in the process of being scheduled. All DDI employees will participate in<br />

this medical surveillance process. More information to follow. (6/1) Discussed medical physical<br />

scheduling. (6/15) No change. (6/22) WCH is working with AMH to schedule all project<br />

persons for physicals and training. (6/29) WCH has scheduled beryllium training, physicals still<br />

in process. (7/6)