Progress Review Meeting<br />

Page 3<br />

111. PROJECT DESIGN DRAWINGS<br />

*Electrical drawings are in process. Diesel storage tank electrical designs and trailer site electrical<br />

as well as as-built drawings. DDI will be re-submitting drawings which will incorporate WCH<br />

comments. DDI to make sure that drawings reflect changes that have occurred recently.<br />

IV.<br />

UPDATED ROLLING 3-4 WEEK LOOK AHEAD SCHEDULE<br />

* See attached.<br />

* Discussed trench scheduled. DDI plans daily to have two primary sorts, two secondary sorts, and<br />

one load-out for now. DDI has begun work in trench DEP. Will perform two (2) loadouts in the<br />

beginning. After DEP trenches are complete, work will be moved to trench G before starting<br />

trench F.<br />

V. WEEKLY PRODUCTION TABLE<br />

* None.<br />

VI.<br />

VII.<br />

VIII.<br />

IX.<br />

MANPOWER<br />

* See attached.<br />

EQUIPMENT<br />

0 See attached.<br />

WORK PACKAGE NEEDS IN ORDER OF PRIORITY AS SET BY DDI<br />

* None.<br />

MATERIAL<br />

* None.<br />

X. QUALITY<br />

" WCH QA in process of scheduled assessments.<br />

* Discussed the importance of proper completion of inspection forms.<br />

XI.<br />

XII.<br />

REQUESTS FOR INFORMATION<br />

* None.<br />

TECHNICAL DATA SUBMITTALS/STATUS<br />

* DDI plans to revise equipment maintenance plan (9/25).<br />

* DDI plans to resubmit fall protection plan<br />

* DDI working on OMP (9/25) and will submit to WCH.<br />

* DDI to resubmit corrected G-02 after reconciliation.<br />

* WCH is reviewing submittal 3-011-001 (Notification of/or Quarterly Inventory Updates of<br />

Chemical Materials/Products Inventory 1/4/2010<br />

" WCH is reviewing submittal 09-005-018 (Equipment Inspection of: Peterbuilt Shuttle Truck 84,<br />

Water Truck 774)<br />

* WCH is reviewing submittals 05-08-001, 002, 003, 004 (Electrical Drawings)<br />

* WCH is reviewing submittal 09-013-OOIA (Traffic Control Plan)