Progress Review Meeting<br />

Page 3<br />

used oil from the site. Any questions about exceptions to this need to be discussed with the WCH<br />

EPL. (5/11) DDI continues to work on completing the OMP with support from the WCH EPL.<br />

DDI plans to submit the OMP next week. (5/18) Submission of OMP pushed out to 6/3/2010.<br />

(5/25) No change. (6/1) DDI is still working on OMP submittal. (6/8) No change, DDI to<br />

submit by 6/24/10. (6/15) DDI is on schedule to meet 6/24 submission. (6/22) WCH has<br />

received OMP and is in review. (6/29) WCH is still reviewing. (7/6) DDI has received<br />

submittal back with WCH comments. DDI requests to remove SPCC submitted from showing as<br />

due since they are working to the OMP. (7/14)<br />

" Discussed Incidental Welding procedure. Surveillance performed, identified necessary changes<br />

to be made for clarifications. (5/18) No update. (5/25) DDI to revise this week. (6/1) DDI to<br />

submit by 6/10/2010. (6/8) DDI commits to submitting no later than 6/24/10. (6/15) DDI on<br />

schedule for submission by 6/24. (6/22) WCH has received and is in review. (6/29) WCH has<br />

returned to DDI status 2. (7/6) DDI has received back and is working through comments. (7/14)<br />

* DDI and WCH are planning to perform confirmatory sampling on one test pit and two trenches<br />

for 100-K-2 on the day the scale is being replaced - June 18. (6/8) This activity was rescheduled<br />

with new date TBD. (6/22) No change. (6/29) No change. (7/6) This will be tentatively<br />

rescheduled for Friday, July 30 pending support availability. (7/14)<br />

* DDI to develop NCR for the suspect/modified lift points on the new truck scale. (6/22) NCR has<br />

been implemented and DDI is developing a documented path forward to address the NCR. (6/29)<br />

No update. It is suggested by WCH QA that a reminder be put into place that a new lift plan will<br />

need to be developed prior to the scale being removed at the end of the project. (7/14)<br />

* DDI to submit REA for 100-K-2 confirmatory sampling. (6/22) DDI to submit by 6/3 0. (6/29)<br />

No change. (7/6) DDI submitted letter with questions about costs related to analysis of<br />

confirmatory sampling activities. WCH commits to providing a response to DDI by 7/19. (7/14)<br />

* Discussed future start-up plans for Trench N. DDI to present plan for Trench N for WCH<br />

concurrence before the start of intrusive activities. (6/22) No change. (7/6) DDI to schedule a<br />

meeting Monday 7/19 with pertinent DDI and WCH personnel to discuss plan for Trench N.<br />

(7/14)<br />

* DDI is scheduling a 25-ton certification scale test for Kenworth trucks on Tuesday, June 29 at<br />

10:00. A WCH engineer will participate in witnessing the test. (6/22) Test rescheduled to 6/3 0.<br />

DDI working to obtain information from G & H for hoist modifications. (6/29) Test, as<br />

performed, was not successful. DDI is making arrangements for another test, tentatively<br />

scheduled for 7/12/20 10. (7/6) A second test was performed without success. DDI is submitting<br />

certifications today for four (4) of the shuttle trucks. These do not include the 22-ton shuttle<br />

trucks. (7/14)<br />

" Discussed the status of plans for handling and disposition of known large canisters in Trench K,<br />

DDI to provide details. (6/29) No update. (7/6) This will be included in the discussion to be<br />

scheduled on Monday afternoon, 7/19. (7/14)<br />

" Discussed Beryllium controls and medical surveillance requirements for Trench I remediation.<br />

(5/25) Medical screen in the process of being scheduled. All DDI employees will participate in<br />

this medical surveillance process. More information to follow. (6/1) Discussed medical physical<br />

scheduling. (6/15) No change. (6/22) WCH is working with AMH to schedule all project<br />

persons for physicals and training. (6/29) WCH has scheduled beryllium training, physicals still<br />

in process. (7/6) WCH has received some beryllium medical appointments (to begin next week)<br />

with the remainder to come. DDI needs to ensure that scheduled employees are aware of and<br />

show up for their scheduled appointments. Missed appointments can further impact the Trench I<br />

Silo schedule. (7/14)