Progress Review Meeting<br />

Page 7<br />

revision. WCH to follow-up. (7/14) WCH will be issuing a revision to this CN by the end of the<br />

week. (7/20) WCH has submitted to DDI. (7/27) No costs per DDI. (8/3)<br />

* WCH returned CN 016 to DDI for corrections and changes. (6/1) No update. (6/8) WCH has<br />

received proposal and is making minor adjustments. (6/22) DDI will resubmit proposal by 7/26.<br />

(7/20) WCH waiting on DDI response to hours needed to change out cable. (7/27) No change.<br />

(8/3)<br />

* WCH is returning CN 007 R. 1 and CN 019 for corrections and changes. (6/8) WCH has<br />

received proposal for CN 007 R. 1 and is reviewing. (6/22) WCH commits to completing review<br />

by 7/19. (7/14) WCH is waiting on proposal from DDI for CN 019. (7/27) WCH has submitted<br />

changes on 7/21 to DDI on CN 007. (8/3)<br />

* WCH has issued CN 026 for the Trench I equipment and materials. (6/22) Discussion about start<br />

of fabrication for Trench I equipment from Jewell. WCH requests DDI confirm that fabrication<br />

started on 7/14. DDI to provide WCH with itemized procurement and delivery schedule for<br />

fabricated equipment. (7/14) DDI waiting on revved contract from Jewell to include the laptop<br />

requirements. When received, the proposal will be resubmitted, anticipate by the end of the<br />

week. (8/3)<br />

o<br />

DDI has not received any information on the Trench I camera specs or equipment<br />

specs for the 400 excavator. They will follow up with the vendor. (5111) Some specs<br />

have been received, but more are needed. Confer with D. Teachout for specifics.<br />

(5/18) WCH is in development of change notice for Trench I work. (5/2 5) No update.<br />

(6/1) DDI is to follow-up ASAP to provide the specs. Trench I operations scheduled<br />

to begin late July/early August. (6/8) WCH discussed concerns (6/15) WCH has<br />

transmitted to DDI CN 026 to provide clamnshell and camera excavation equipment.<br />

(6/22) Proposal to be provided to WCH by close of business this week. (6/29) WCH<br />

has requested a delivery schedule for equipment. DDI will provide drawings/details<br />

for equipment (7/6) DDI provided schedule for equipment fabrication from Jewell.<br />

(7/27)<br />

" DDI has submitted proposal today for CN 012, WCH to review. (7/14) WCH is reviewing<br />

proposal, but still needs the signed Change Notice acknowledgement from DDI. (7/20) NO<br />

update. (7/27) WCH is reviewing. (8/3)<br />

* WCH will be issuing CN 027 to DDI today. (7/27) WCH issued 7/28 to DDI. (8/3).<br />

XIV.<br />

XV.<br />

CORRESPONDENCE (since last meeting)<br />

0 Weekly Progress Review Meeting Minutes of 8/3/2010<br />

IN VOICE AND PAYMENT STATUS<br />

*Discussion of completion incentive by trench. Per the contract DDI has the potential for partial<br />

release of retention. For Trenches D, E, P and G one-half of the retainage may be released when<br />

completed. (7/27) A topographical survey will be required upon completion concurrence from<br />

WCH. (8/3)<br />

*DDI to submit invoice this week for July work.<br />

o As energized as-builts have not yet been received, WCH anticipates additional 15%<br />

withholding from July payment. (7/27) WCH will confirm if any change to retainage percent<br />

by the end of the day. (8/3)