Progress Review Meeting<br />

Page 4<br />

truck is under lease agreement with DDI not Watts for use at 118-K. (10/12)<br />

VIII. WORK PACKAGE NEEDS IN ORDER OF PRIORITY AS SET BY DDI<br />

"WCH intends to begin working on Trench I silo work packages in early August. Tentative<br />

meeting set for 8/16 to discuss work package for Trench I silos. WCH to confirm with planners<br />

on schedule. (8/3) When the initial work package is developed, craft will be involved in the fine<br />

tuning of the WP. (8/10) Meeting postponed to Monday, 8/23. (8/17) Meeting moved to<br />

Wednesday 8/25 at 8:00. In the near future a WCH planner will be on site three days a week for<br />

support with work packages and technical procedure needs. (8/24) Informal review of existing<br />

work packages has begun by WCH Planners. WCH will involve DDI field personnel as the work<br />

draws closer. (8/3 1) Ongoing. (9/7). WCH would like to begin including DDI SS in the work<br />

package planning process. (9/2 8)<br />

* Meeting to discuss the Sort and Loadout JHA Rev. I scheduled for 10/6/10 at 8:00. (10/5)<br />

Continuing. (10/12)<br />

IX.<br />

MATERIAL<br />

* Dust Bond and propylene glycol now on site. (10/12)<br />

X. QUALITY<br />

*WCH QA will be conducting surveillance on contract flowdown and review of sub-tier QA<br />

programs. (5/25) This is ongoing. (6/1) There may be an issue with the flowdown of submittals<br />

between Watts and DDI. WCH QA suggests that DDI review their contract to determine if there<br />

is a breakdown. Per the WCH QA this is becoming an item of increasing interest for DOE and<br />

WCH. (6/8) DDI should be prepared for an inspection of their QA plan and flow-downs by<br />

WCI- QA in the near future. (6/29) DDI provided copy of surveillance by WCH QA. This<br />

surveillance will be ongoing this week and next. (7/14) The surveillance will be conducted on<br />

7/22 for this site. (7/20) This surveillance is ongoing to additional sub-tiers. Results are not<br />

anticipated to be positive. There appears to be serious issues with flowdown of DDI QA plan to<br />

sub tiers. WCH QA is concerned about how the QA plan is being implemented by sub-tiers.<br />

These issues are of considerable concern to WCH. (7/27) DDI and WCH QA to meet to discuss<br />

flow downs. (8/3) WCH QA will be issuing letter to DDI outlining the details of the<br />

surveillance results. (9/28) DDI is revising their QA plan, will be Rev. 1. (10/5)<br />

o WCH QA still has concern about DDI fiowdown to WCI. DDI indicated that WCI has<br />

provided letter indicating they intend to work to the DDI QA plan. DDI indicated they have<br />

not assessed WCI to determine that WCI is adhering to the QA plan. (8/10) DDI would like<br />

a response in writing outlining the concerns that WCH QA has that WCI is not working to the<br />

DDI QA program. (8/17) WCH will be issuing SDR this week to DDI for deficiencies. (FR-<br />

2010-IF-0664-SDR-023) (8/24) DDI has received the SDR and indicated they will address<br />

issues. (8/3 1) DDI will be submitting QA Program rewrite this week. (9/7) This has been<br />

pushed out. (9/22) WCH QA and DDI PM to meet to discuss SDR and response. (9/28)<br />

Discussed SDR response for QA flowdown. (10/12)<br />

o<br />

DDI developing NCR #2, CAP to be provided to WCH for acceptance prior to resumption of<br />

use of breathing air equipment. (9/22) WCH to provide SDR today to DDI. (9/28)<br />

" Discussed QA audit (DOE) from last week. DOE cited DDI's failure to implement QA plan.<br />

(10/5)<br />

" WCH to issue SDR to DDI for IH issues. (10/12)