Progress Review Meeting<br />

Page 4<br />

*WCH intends to begin working on Trench I silo work packages in early August. Tentative<br />

meeting set for 8/16 to discuss work package for Trench I silos. WCH to confirm with planners<br />

on schedule. (8/3) When the initial work package is developed, craft will be involved in the fine<br />

tuning of the WP. (8/10) Meeting postponed to Monday, 8/23. (8/17) Meeting moved to<br />

Wednesday 8/25 at 8:00. In the near future a WCH planner will be on site three days a week for<br />

support with work packages and technical procedure needs. (8/24) Informal review of existing<br />

work packages has begun by WCH Planners. WCH will involve DDI field personnel as the work<br />

draws closer. (8/3 1) Ongoing. (9/7). WCH would like to begin including DDI SS in the work<br />

package planning process. (9/28) Meeting scheduled for Thursday, 10/28 to discuss work<br />

package needs relating to overburden removal to locate the tops of the silos in Trench 1. (10/26)<br />

The plan is to have the JHA complete by 11/18/2010. There may be additional changes or tweaks<br />

after the dry runs are completed. (11/16) WCH SMRT review scheduled, final work package<br />

should be available for approval next week. (11/30) No change, plan to have review by the end<br />

of the week. (12/7) Work Package is with the planners and should be signed off by the end of<br />

this week. (12/14) Trench I work package is complete. (12/28) Crew briefing on Trench I work<br />

package is scheduled for 1/5-6/11. (1/4) Work package briefing with the crew was held on<br />

IX.<br />

MATERIAL<br />

* None.<br />

X. QUALITY<br />

" WCH QA informed DDI that SCI training is available free of charge and recommended they send<br />

some people through the training. Bob Carter will be administering the training. (1/4) Jim<br />

Soulia is planning to attend. (1/12)<br />

" WCH QA will be participating in a factual accuracy meeting with DOE tomorrow about the DDI<br />

QA plan. (1/4) WCH did not receive any take away input from the meeting. (1/12)<br />

" WCH QA provided DDI with copy of assessments coming up in the near future. (1/4)<br />

FUTURE ASSESSMENTS<br />

* WCH will be issuing SDR this week to DDI for deficiencies for DDI Procurement<br />

Controls/Control or Purchased Itemns and Services. (FR-2010-IF-0664-SDR-023) (8/24) WCH<br />

has received and accepted the CAP from DDI for SDR-023. Corrective action timeline has been<br />

extended to January. (11/9) WCI- to perform surveillance for CAP implementation due 2/1/1 1.<br />

(1/12)<br />

" WCH to issue SDR (FR-201 0-IF-0749-SDR-024) to DDI for IH breathing air calibration issues.<br />

(10/12) WCH has received CAP from DDI. (11/9) WCH to perform follow-up surveillance for<br />

implementation of CAP. (11/30) WCH has accepted the CAP for this SDR. WCH will perform<br />

final surveillance in the near future to close this item. Surveillance will be completed by 2/24/Il.<br />

(1/12)<br />

* WCH to provide SDR (FR-201 0-IF-0826-SDR-02 5) today to DDI for IH equipment past the<br />

calibration date. (9/28) WCH has received CAP from DDI. (11/9) WCH to perform follow-up<br />

surveillance for implementation of CAP. (11/30)<br />

" WCH QA shared with DDI a checklist outlining subcontractor responsibilities at related to subtier<br />

contractors. (1/12)<br />

XI.<br />

REQUESTS FOR INFORMATION<br />

*None.