Progress Review Meeting<br />

Page 4<br />

" No intrusive work can be started relative to Trench I until the PSR has been approved and signed<br />

off by WCH management.<br />

" See attached.<br />

VI.<br />

VII.<br />

MANPOWER<br />

* See attached.<br />

" Recently WCH observed operators driving water trucks. Per the HSSA contract that is not<br />

allowable. DDI will issue a letter to their sub-tier, WCI concerning this. (8/10) DDI has not yet<br />

issued letter. (8/17) No update. (8/24)<br />

* A new laborer has been hired as a gate guard. (9/7)<br />

EQUIPMENT<br />

" See attached.<br />

" The 225 excavator will be moved to allow for decontamination and will eventually be moved off<br />

site. (8/24) This is in process. (9/7)<br />

" The 400 excavator will be decontaminated when the 450 excavator arrives on site. (9/7)<br />

VIII. WORK PACKAGE NEEDS IN ORDER OF PRIORITY AS SET BY DDI<br />

" None.<br />

* WCH intends to begin working on Trench I silo work packages in early August. Tentative<br />

meeting set for 8/16 to discuss work package for Trench I silos. WCH to confirm with planners<br />

on schedule. (8/3) When the initial work package is developed, craft will be involved in the fine<br />

tuning of the WP. (8/10) Meeting postponed to Monday, 8/23. (8/17) Meeting moved to<br />

Wednesday 8/25 at 8:00. In the near future a WCH planner will be on site three days a week for<br />

support with work packages and technical procedure needs. (8/24) Informal review of existing<br />

work packages has begun by WCH Planners. WCH will involve DDI field personnel as the work<br />

draws closer. (8/3 1) Ongoing. (9/7)<br />

IX.<br />

MATERIAL<br />

*DDI is planning to begin the process of ordering ecology blocks that will be used in the Trench I<br />

Silo remnediation. (7/27) DDI is planning for approximately 150 ecology blocks. (8/3)<br />

0 WCH will be issuing an additional change notice for trench I that will require provision of<br />

means and methods as well as materials such as ecology blocks. (8/10) DDI should plan for<br />

draft specification from WCH by the end of the week. (8/3 1) WCH still waiting on<br />

specifications from Design Engineering group to finalize issuing change notice for remainder<br />

of Trench I changes.<br />

X. QUALITY<br />

*WCH QA will be conducting surveillance on contract flowdown and review of sub-tier QA<br />

programs. (5/25) This is ongoing. (6/1) There may be an issue with the flowdown of submittals<br />

between Watts and DDI. WCH QA suggests that DDI review their contract to determnine if there<br />

is a breakdown. Per the WCH QA this is becoming an item of increasing interest for DOE and<br />

WCH. (6/8) DDI should be prepared for an inspection of their QA plan and flow-downs by<br />

WCH QA in the near future. (6/29) DDI provided copy of surveillance by WCH QA. This<br />

surveillance will be ongoing this week and next. (7/14) The surveillance will be conducted on<br />

7/22 for this site. (7/20) This surveillance is ongoing to additional sub-tiers. Results are not<br />

anticipated to be positive. There appears to be serious issues with flowdown of DDI QA plan to<br />

sub tiers. WCH QA is concerned about how the QA plan is being implemented by sub-tiers.