Progress Review Meeting<br />

Page 6<br />

employee social security numbers as identifier. DDI indicates they have not yet received this<br />

revision. WCH to follow-up. (7/14)<br />

* WCH returned CN 016 to DDI for corrections and changes. (6/ 1) No update. (6/8) WCH has<br />

received proposal and is making minor adjustments. (6/22)<br />

" WCH is returning CN 007 R. 1 and CN 019 for corrections and changes. (6/8) WCH has<br />

received proposal for CN 007 R. 1 and is reviewing. (6/22) WCH commits to completing review<br />

by 7/19. (7/14)<br />

" WCH has issued CN 026 for the Trench I equipment and materials. (6/22) Discussion about start<br />

of fabrication for Trench I equipment from Jewell. WCH requests DDI confirm that fabrication<br />

started on 7/14. DDI to provide WCH with itemized procurement and delivery schedule for<br />

fabricated equipment. (7/14)<br />

o DDI has not received any information on the Trench I camera specs or equipment<br />

specs for the 400 excavator. They will follow up with the vendor. (5/11) Some specs<br />

have been received, but more are needed. Confer with D. Teachout for specifics.<br />

(5/18) WCH is in development of change notice for Trench I work. (5/25) No update.<br />

(6/1) DDI is to follow-up ASAP to provide the specs. Trench I operations scheduled<br />

to begin late July/early August. (6/8) WCH discussed concerns (6/15) WCH has<br />

transmitted to DDI CN 026 to provide clamshell and camera excavation equipment.<br />

(6/22) Proposal to be provided to WCH by close of business this week. (6/29) WCH<br />

has requested a delivery schedule for equipment. DDI will provide drawings/details<br />

for equipment (7/6)<br />

" DDI has submitted proposal today for CN 016, WCH to review. (7/14)<br />

XIV.<br />

XV.<br />

XVI.<br />

CORRESPONDENCE<br />

* Letter from DDI: Written Change Notice Request and Schedule Modification Request<br />

* Transmittal from DDI: Proposal for Change Notice 026<br />

" Letter from DDI: Water Requirements fort he 118 -K- I Burial Ground Contract/Notice of<br />

Deficiency No. 151448<br />

* Resume for Glenn Holbrook, CIH<br />

" Transmittal from DDI: Proposal for Change Notice 012<br />

* E-mail to DDI: Acceptance of Glenn Holbrook, CIII<br />

* Weekly Progress Review Meeting Minutes of 7/6/2010<br />

IN VOICE AND PAYMENT STATUS<br />

* WCH made modifications to June invoice. WCH will not be withholding additional 15% from<br />

this billing.<br />

" Discussion of completion incentive by trench. Per Exhibit D of the contract DDI has the potential<br />

for partial release of retention.<br />

OTHER COMMENTS/NEW ACTION ITEMS<br />

* None.<br />

Attachment(s): As noted above.