Progress Review Meeting<br />

Page 5<br />

having the drawing resubmitted by 7/21. (7/14) No change. (7/20) The drawing needs to revved<br />

to reflect 15 amp versus 20 amp fuses. (7/27)<br />

*Water line as-builts are being marked up for WCH review prior to being submitted. (6/1) No<br />

change. WCH stressed that the as-builts need to indicate the location of the water lines from hook<br />

up at the fence to the high tower. (6/8) No change. (6/15) No change. (6/22) WCH to provide<br />

new drawing number for the as-built drawing. (6/29) WCH will also provide a CADD base file<br />

to DDI for this drawing. (7/6) DDI has received base CADD file and is in process of updating<br />

drawing. They commit to resubmitting drawing by 7/2 1. (7/14) DDI has had issues with the<br />

CADD file, submission bumped to 7/26. (7/20) DDI is reviewing the cost of drawing; anticipate<br />

submittal of drawing by 8/3. (7/27)<br />

IV.<br />

UPDATED ROLLING 3-4 WEEK LOOK AHEAD SCHEDULE<br />

*None provided at the time of the meeting.<br />

o Not provided by DDI as a result of a unilateral decision by DDI corporate.<br />

V. WEEKLY PRODUCTION TABLE<br />

* No intrusive work can be started relative to Trench I until the PSR has been approved and signed<br />

off by WCH management.<br />

" No production table has been provided. This would include quantity of can counts, updated<br />

weekly, separated and denoted by trench. DDI feels they are able to provide this weekly.<br />

VI.<br />

VII.<br />

MANPOWER<br />

* See attached.<br />

* DDI is down one operator. They will address with their sub-tier about filling this position. No<br />

update. (7/20) Now down a teamster in addition to an operator. No update on filling either<br />

position. (7/27)<br />

EQUIPMENT<br />

* See attached.<br />

* Rock truck shown on the report is not on site. (7/20) Rock truck is returning 7/27. (7/27)<br />

VIII. WORK PACKAGE NEEDS IN ORDER OF PRIORITY AS SET BY DDI<br />

" None.<br />

" WCH intends to begin working on Trench I silo work packages in early August.<br />

IX.<br />

MATERIAL<br />

*DDI to begin the process of ordering ecology block that will be used in the Trench I Silo<br />

remediation.<br />

X. QUALITY<br />

*The Kenworth haul trucks are on hold for use with 25-ton cans until final certification data is<br />

provided. Submittal for certification was returned status 3. No update (5/4). No update. (5/11)<br />

No update. (5/18) No update. (6/1) No update. (6/8)<br />

*WCH issued SDR (FR-201 0-I17-0092-017) to DDI on 5/24/2010 for shuttle truck<br />

specifications. (5/25) No update. (6/1) No update. (6/8) DDI to provide CAR by 6/24/2010.<br />

(6/22) WCH received CAR today. (6/29) WCH is in review of the CAR (7/14) WCH QA<br />

would like DDI to update the letter provided in response with current information and dates.<br />

(7/20) DDI to submit letter with updated information on 7/27. (7/27)