Progress Review Meeting<br />

Page 6<br />

*Electrical Drawings for electrical tie-ins, as-builts and diesel tank electrical design have been<br />

submitted to WCH. Review and conmments to be returned to RDC today. DDI incorporating<br />

comments and will resubmit. DDI to submit by 1/28/2010. WCH has received, in<br />

preliminary review, will return this week. WCH returned to DDI, status 2, with comments.<br />

DDI will be doing a walkdown with Mr. Teachout to incorporate comments and will resubmit<br />

drawings for approval. DDI to check on status. DDI waiting on North Point. DDI still<br />

waiting on North Point. They have exceeded the 30-day expected response to a returned<br />

submittal. DDI to follow up with North Point again this week. No update, still with DDI<br />

(4/20). No update (4/27). No update (5/4). No update from DDI. WCH issued SDR. (5/18)<br />

No update. (5/2 5) No update. (6/8) WCH is in review of drawing. (6/29) DDI has received<br />

the review comments from WCH and is working to get the drawing updated. They commit to<br />

having the drawing resubmitted by 7-21. (7/14)<br />

" WCH return traffic control drawings to DDI, status 2. DDI will be resubmitting soon<br />

incorporating the WCH comments. DDI to submit this week. Drawings are with North Point for<br />

revision and will be resubmitted upon their return. DDI is well beyond the 30-day resubmission<br />

for updated drawings. WCH will be issuing an SDR regarding this issue. DDI has indicated they<br />

are working on a deficiency letter which will be submitted to Watts for this and several other<br />

deficiencies. (5/11) No update. (5/18) No update. (5/25) WCH received traffic control submittal<br />

6/3 and is in review of same. (6/8) WCH has returned to DDI status 2. (6/22) No change. (6/29)<br />

They commit to resubmitting drawing by 7/21 (7/14). DDI will install signs to match the traffic<br />

control drawing then resubmit. (7/20)<br />

" WCH requests as-built drawings of the energized water system. No update (5/4). No update.<br />

(5/11) SDR provided, no update. (5/18) No update. (5/25) No update. (6/8) DDI submitted redline<br />

copies. WCH will provide a drawing number to DDI. (6/29) DDI has received the reviewed<br />

comments from WCH and is working to get the drawing updated. WCH has provided base<br />

CADD file and DDI is in process of updating drawing. (7/14). DDI is working with their<br />

design group to update the drawings. (7/20)