Progress Review Meeting<br />

Page 5<br />

XIII.<br />

XIV.<br />

XV.<br />

XVI.<br />

CHANGE NOTICES/STATUS/CHANGE ORDERS<br />

* See attached.<br />

CORRESPONDENCE<br />

" Letter from DDI: Monthly IH Report for April 2010 (per HASP)<br />

" Weekly Progress Review Meeting Minutes of 5/11/2010<br />

* Letter from DDI: Recall Work Performed Paperwork<br />

INVOICE AND PAYMENT STATUS<br />

* April invoice is in WCH approval process.<br />

OTHER COMMENTS/NEW ACTION ITEMS<br />

* DDIs new <strong>Site</strong> Safety Officer, Ilene Strong, started on Monday. Whitney Sexsmith's last day is<br />

to be Thursday 5/13.<br />

* DDI has not yet responded to the Subcontractor Deficiency Report - FR-201 0-IF-0045-SDR-0 10.<br />

* An All-Hands Meeting will be held next week at the Three Rivers Convention Center. This<br />

meeting will be discussing the site-wide beryllium program. More info to follow.<br />

" Tuesday and Wednesday of next week is the Safety Expo to be held at TRAC. The site will<br />

shutdown early to allow all employees (WCH, ESHI and all Subcontractor) to attend. More<br />

information to follow.<br />

* DDI has not received any information on the Trench I camera specs or equipment specs for the<br />

400 excavator. They will follow up with the vendor.<br />

* There are several safety items that need DDI attention from last week's safety walkdown.<br />

(Cover/Storage fort he breathing air bottles, cord trees for the fans used in the field, fixative hose<br />

at the tent, and move the batteries charging in the conex.)<br />

Attachment(s): As noted above.