17.12.2013 Views

FOI_2011-00646_Enclosure - Hanford Site

FOI_2011-00646_Enclosure - Hanford Site

FOI_2011-00646_Enclosure - Hanford Site

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Washington<br />

closure<br />

WCH <strong>Hanford</strong><br />

Meeting Minutes<br />

CCN: 152515<br />

Mal"Q"MWEEKLY PROGRESS REVIEW MEETING C008753A00<br />

Distribution<br />

11111=191"M<br />

Christopher L. Beach<br />

August 24, 20 10<br />

ATEDE<br />

DSTRIBTIO<br />

E. L. Adamson X3-40 D. Bollinger (DDI)<br />

C. L. Beach X3-16 R. D. Cantwell N3-30<br />

Q. L. Grist X3-16 R. W. Cross 1-4-25<br />

R. Ferguson (DDI) X3-17 T. Dance (DDI) X3-17<br />

C. Flowers (DDI) X3-17 R. A. Dodd 1H4-24<br />

A. Gagnon X9-08 T. A. Foster N3-30<br />

J. A. Heard H4-17 R. Ganapathy X3-40<br />

S. E.Parnell X3-16 R. T. Hansen 114-17<br />

M. Sherman (DDI) X3-17 S. J. Huddleston X3-16<br />

H. C. Weber (DDI) X3-16 W. R. Junkins X3-16<br />

H. Williams III X3-16 D. G. Saueressig N3-30<br />

D. B. Teachout X3-16<br />

J. Zeisloft A3-04<br />

Project File, X3-16<br />

Records and Document Control H14-11I<br />

A meeting on the above subject was held on August 24, 2010 at 118-K, MO-755.<br />

1. SAFETY<br />

*Safety topic: As the days are getting shorter, be alert for wildlife crossing the road during<br />

commutes. A deer was hit on the River Road during the Monday morning commute.<br />

II.<br />

ACTION ITEMS FROM LAST MEETING/STATUS<br />

*PRC Deputy Fire Marshall has requested sketch of water system configuration that will be<br />

constructed. DDI to provide. The excavation permit and non-emergency hydrant tie-in permit<br />

approvals are with the CHPRC 100-K Fire Protection Engineer pending their approval of this<br />

system. Additional request has been made for CAD drawings of this configuration by the Fire<br />

Protection Engineer. WCH has followed up on status and has resolved CHPRC concerns and<br />

requests. Currently just waiting on the permits to be issued by CHPRC. Discussed 150 gpm<br />

restrictor to be installed at the hydrant tie-in as well as an additional restrictor at the water high<br />

tank. Permits scheduled to be complete by 1/14/20 10. Still waiting on permits from CHPRC.<br />

WCH following up. Hydrant permit is in hand, waiting for excavation permit. Plan to perform<br />