Progress Review Meeting<br />

Page 5<br />

XI.<br />

XII.<br />

REQUESTS FOR INFORMATION<br />

*DDI will be issuing an RFI for the scheduler position, duties and WCH expectations. No update<br />

(5/4). No update. (5/11) No change. (5/18) Received, WCH in review. (5/25) No update. (6/1)<br />

WCH commits to having a response to DDI no later than 6/15. (6/8)<br />

TECHNICAL DATA SUBMITTALS/STATUS<br />

* See attached.<br />

Electrical Drawings for electrical tie-ins, as-builts and diesel tank electrical design have been<br />

submitted to WCH. Review and comments to be returned to RDC today. DDI incorporating<br />

comments and will resubmit. DDI to submit by 1/28/20 10. WCH has received, in<br />

preliminary review, will return this week. WCH returned to DDI, status 2, with comments.<br />

DDI will be doing a walkdown with Mr. Teachout to incorporate comments and will resubmit<br />

drawings for approval. DDI to check on status. DDI waiting on North Point. DDI still<br />

waiting on North Point. They have exceeded the 30-day expected response to a returned<br />

submittal. DDI to follow up with North Point again this week. No update, still with DDI<br />

(4/20). No update (4/27). No update (5/4). No update from DDI. WCH issued SDR. (5/18)<br />

No update. (5/25) No update. (6/8)<br />

* WCH return traffic control drawings to DDI, status 2. DDI will be resubmitting soon<br />

incorporating the WCH comments. DDI to submit this week. Drawings are with North Point for<br />

revision and will be resubmitted upon their return. DDI is well beyond the 30-day resubmission<br />

for updated drawings. WCH will be issuing an SDR regarding this issue. DDI has indicated they<br />

are working on a deficiency letter which will be submitted to Watts for this and several other<br />

deficiencies. (5/11) No update. (5/18) No update. (5/25) WCH received traffic control submittal<br />

6/3 and is in review of same. (6/8)<br />

" WCH reques ts as-built drawings of the energized water system. No update (5/4). No update.<br />

(5111) SDR provided, no update. (5/18) No update. (5/25) No update. (6/8)<br />

XIII. CHANGE NOTICES/STATUS/CHANGE ORDERS<br />

* See attached.<br />

* DDI can expect to see revision soon to Change Notice 025 regarding use of last for digits of<br />

employee social security numbers as identifier.<br />

* WCH returned CN 016 to DDI for corrections and changes. (6/1) No update. (6/8)<br />

" WCH is returning CN 007 R. 1 and CN 0 19 for corrections and changes. (6/8)<br />

* WCH is issuing CN 026 for the Trench I equipment and materials.<br />

XIV.<br />

XV.<br />

CORRESPONDENCE<br />

* Letter to DDI: Deficiency Reports<br />

IN VOICE AND PAYMENT STATUS<br />

*WCH has received billing for May and is reviewing.<br />

o WCH will be sending a letter to DDI indicating that WCH intends to withhold payment until<br />

the overdue as-built drawings are received. DDI requested WCH to provide value of<br />

holdback. WCH agreed to communicate this by the end of the day. (6/8) Proficiency<br />

withholding (retainage) to be released when as-builts are received and deemed compliant.<br />

(6/15)