Progress Review Meeting<br />

Page 7<br />

XIII.<br />

XIV.<br />

XV.<br />

CHANGE NOTICES/STATUS/CHANGE ORDERS<br />

* See attached.<br />

" DDI can expect to see revision soon to Change Notice 025 regarding use of last four digits of<br />

employee social security numbers as identifier. DDI indicates they have not yet received this<br />

revision. WCH to follow-up. (7/14) WCH will be issuing a revision to this CN by the end of the<br />

week. (7/20)<br />

* WCH returned CN 016 to DDI for corrections and changes. (6/1) No update. (6/8) WCH has<br />

received proposal and is making minor adjustments. (6/22) DDI will resubmit proposal by 7/26.<br />

(7/20)<br />

" WCH is returning CN 007 R. 1 and CN 019 for corrections and changes. (6/8) WCH has<br />

received proposal for CN 007 R. 1 and is reviewing. (6/22) WCH commits to completing review<br />

by 7/19. (7/14)<br />

* WCII has issued CN 026 for the Trench I equipment and materials. (6/22) Discussion about start<br />

of fabrication for Trench I equipment from Jewell. WCH requests DDI confirm that fabrication<br />

started on 7/14. DDI to provide WCH with itemized procurement and delivery schedule for<br />

fabricated equipment. (7/14)<br />

o<br />

DDI has not received any information on the Trench I camera specs or equipment<br />

specs for the 400 excavator. They will follow up with the vendor. (5/11) Some specs<br />

have been received, but more are needed. Confer with D. Teachout for specifics.<br />

(5/18) WCH is in development of change notice for Trench I work. (5/25) No update.<br />

(6/1) DDI is to follow-up ASAP to provide the specs. Trench I operations scheduled<br />

to begin late July/early August. (6/8) WCH discussed concerns (6/15) WCH has<br />

transmitted to DDI CN 026 to provide clamshell and camera excavation equipment.<br />

(6/22) Proposal to be provided to WCH by close of business this week. (6/29) WCH<br />

has requested a delivery schedule for equipment. DDI will provide drawings/details<br />

for equipment (7/6)<br />

" DDI has submitted proposal today for CN 012, WCH to review. (7/14) WCH is reviewing<br />

proposal, but still needs the signed Change Notice acknowledgement from DDI. (7/20)<br />

CORRESPONDENCE (since last meeting)<br />

* Transmittal from DDI: Acceptance for Change Notice 0 12<br />

" Weekly Progress Review Meeting Minutes of 7/14/2010<br />

INVOICE AND PAYMENT STATUS<br />

* Reminder that this Sunday is the end of the July reporting period. DDI should note that WCH<br />

needs to receive the electrical and energized water system drawings or the additional 15% will be<br />

deducted from the July payment.<br />

0 Discussion of completion incentive by trench. Per the contract DDI has the potential for partial<br />

release of retention.