Progress Review Meeting<br />

Page 3<br />

" DDI will be providing calcium chloride for the water system when it is operational. Before<br />

Trench K is opened up, DDI to have calcium chloride on site for dust control. DDI to look into<br />

utilizing Dust Bond in trenches K, N, 0 and 1. DDI to provide mixture ratios for WCH profile.<br />

DDI is looking into the availability of having Dust Bond totes on site for use with dust control.<br />

DDI to have calcium chloride on site before opening up Trench K excavations. No update (4/20).<br />

DDI indicated the plan is to have a 250 gallon tote that will be used through the injection system<br />

tied into the water system (4/27). 250 pound tote is now on site. The temporary plan of use will<br />

be to draw from the tote into the trucks using a hand pump. This is the solution until the injection<br />

system is installed and working properly (5/4).<br />

* DDI evaluating a location for truck washing. This will be coordinated with the WCH EPL. This<br />

will be set up next to the high tank. WCH EPL will be onsite this week to assist with designating<br />

a location. WCH EPL is in review of proposed location with preference for location in the AOC<br />

(4/27). WCH EPL has approved the truck wash down station at the water tank. Radiological<br />

courtesy surveys will be completed on the trucks prior to wash down of undercarriage (5/4).<br />

* WCH has three confirmatory sampling sites what will require DDI equipment support. More<br />

information will be provided soon. WCH pushing for an April timeframe to perform this work.<br />

A walkdown of one of the sites will be occurring today. WCH will schedule a discussion for next<br />

week to discuss the excavation of the two or 3 sites that are included in the current contract.<br />

Potholing to commence 5/17/2010 when DDL's new sampler has completed her training. A<br />

meeting will be held prior to the sampling to ensure that DDI has everything on hand to support<br />

the excavation activities for confirmatory sampling at 600-29 (4/27). On track to have sampler<br />

training in place by 5/17/20 10 (5/4).<br />

" Discuss implementation and oversight of equipment maintenance plan with the resignation of the<br />

DDI mechanic. DDI working to bring on project mechanic. WCH suggests that DDI review their<br />

equipment maintenance processes, particularly with regards to equipment daily inspections and<br />

how repairs will be made (4/27). Daily inspections are occurring, will have an offsite mechanic<br />

support the project as needed. DDI discussing with their subcontractor that this may have<br />

production impacts. (5/4)<br />

" Discussed issue of inaccurate scale weights. DDI has instructed Watts to install a new scale. The<br />

scale is part of the contract between Watts and DDI. WCH asks that the work be completed no<br />

later than the end of May with work to be completed on weekends so not to take away from<br />

production. (5/4)<br />

* An informal meeting with WCH, DDI and ESHI will be scheduled to discuss start and stop times<br />

in the HRA. (4/27)<br />

" DDI is reminded that Daily Reports are to be submitted to WCH the following day. If the person<br />

who normally completes these is out, a back up needs to be identified and trained. This continues<br />

to be a challenge. (4/27)<br />

" There is an issue with not having Tyvec booties for some site personnel when they are required to<br />

enter the trenches for sampling. DDI commits to getting some on site immediately. DDI has<br />

procured, will provide arrival date. (5/4)<br />

* DDI needs to survey signage used in the CR-Z postings. Currently some signs state "Caution"<br />

while others on the same rope state "Danger". The correct warning level for the CRZ is<br />

"Caution". DDI will address this. (4/27) No change (5/4).<br />

* DDI asked that WCH clarify the definition of anomalies. There seems to be some confusion on<br />

DDI's part what actually constitutes an anomaly. No update. A meeting will e held to discuss<br />