Progress Review Meeting<br />

Page 3<br />

finalization meeting this afternoon. (1/4) BWP has been approved and is in the process of being<br />

signed off. It is expected that this will be completed this week. Once signatures are obtained, the<br />

craft will be briefed on the BWPT. (1/12) BWPT was briefed with the crew on 1/13. (1/18) A<br />

checklist for bringing equipment in/out of the BCA has been developed; the crew briefed, and is<br />

being implemented for use. (1/25)<br />

* Planned dry run for Trench I to begin 11/29. (11/16) Start pushed out due to weather. (11/30)<br />

Need to pinpoint starting dates for dry runs now that equipment is located in the HIRA. WCH to<br />

review the PSR to determine what will be evaluated for readiness from the dry run. (12/7) A dry<br />

run checklist will be developed after the holidays for the 400 excavator. (12/14) Dry run in<br />

Trench A to begin 1/3/11 as planned. (12/28) Dry runs have been moved to 1/6. (1/4) Dry runs<br />

utilizing Trench A were performed on 1/6-11, WCH RE currently working on video connection<br />

troubleshooting. (1/12) All cameras are now working, continuing mock-ups. Some work<br />

package and RWP issues relating to the cone penetrometers are being resolved. (1/ 18)<br />

* Trench I work package training to begin Tuesday 1/4/11 after the POD. (1/4) Completed 1/5/11.<br />

(1/12) Before work can begin, a detailed briefing of the work packing will be given to the Trench<br />

I Silo work crew. (1/18)<br />

" Trench I RWP and BWP training to begin Wednesday 1/5/11 after the POD. (1/4) The RWP was<br />

briefed with the crew on 1/6/11. (1/12) The RWP has been rev'd removing issues relating to the<br />

cone penetrometers and lids. The crew has been briefed on the changes. It is anticipated that the<br />

RWP might be rev'd again as a result of comments from the DNFSB. (1/25)<br />

1I1. PROJECT DESIGN DRAWINGS<br />

0 None.<br />

IV.<br />

UPDATED ROLLING 3-4 WEEK LOOK AHEAD SCHEDULE<br />

* See attached.<br />

" Trench I work package training scheduled for 1/5/11 after the POD. (1/4) Crew briefing<br />

performed 1/5/11. (1/12) A work package revision is being completed and will be briefed by the<br />

crew before work begins. (1/25)<br />

* PSR in final review and plans are for WCH to have it available to be signed off Monday or<br />

Tuesday of next week. (1/4) PSR sign off has been rescheduled for Monday, 1/17/11. (1/12)<br />

o<br />

o<br />

After PSR is signed off, cone penetrometers and lids will be pulled.<br />

Block wall will be completed. (1/4) The first layer of the block wall has been completed.<br />

Once the cone penetrometers and lids are removed, the remainder of the wall will be<br />

constructed. (1/12) Final construction of the block wall will be complete by the end of this<br />

week. (1/25)<br />

V. MANPOWER<br />

* No changes from last week.<br />

VI.<br />

VII.<br />

EQUIPMENT<br />

" No changes from last week.<br />

* A cable change on shuttle truck #74 was completed over the weekend. (1/25)<br />

WORK PACKAGE NEEDS IN ORDER OF PRIORITY AS SET BY DDI<br />

* None.