Progress Review Meeting<br />

Page 2<br />

111. PROJECT DESIGN DRAWINGS<br />

* None.<br />

IV.<br />

UPDATED ROLLING 3-4 WEEK LOOK AHEAD SCHEDULE<br />

* See attached 3-week look ahead schedule provided by DDI. Training is going well.<br />

V. WEEKLY PRODUCTION TABLE<br />

" Additional discussion of upcoming submittals due. DDI provided schedule update.<br />

" Mobilization:<br />

*RCT and Change Trailer to arrive on Monday, 8/24. Balance of trailers to arrive by the end<br />

of that week.<br />

* Training requirements for mobilization are HIM, HASP, IWCP and HGET<br />

VI.<br />

VII.<br />

VIII.<br />

IX.<br />

MANPOWER<br />

*DDI needs to schedule necessary AMH appointment and Hammer Training for crews. Update<br />

- this is not expected to be an issue, anticipate completion around September 9, 2009.<br />

EQUIPMENT<br />

* Heavy equipment inspections scheduled for the week of September 1 at Watts' yard in<br />

Kennewick.<br />

WORK PACKAGE NEEDS IN ORDER OF PRIORITY AS SET BY DDI<br />

* Work packages (USQ screening) to be performed prior to 8/24/09.<br />

MATERIAL<br />

* None.<br />

X. QUALITY<br />

0 None.<br />

XI.<br />

XII.<br />

XIII.<br />

XIV.<br />

REQUESTS FOR INFORMATION<br />

" CNOO1I to be transmitted this week.<br />

* CN002 relating to the tent will be transmitted next week.<br />

TECHNICAL DATA SUBMITTALS/STATUS<br />

" DDI submitted copy of their internal submission log. See attached.<br />

* Discussion held about timing of Lead Handling Plan, Drum Handling Plan, etc. submittals.<br />

CHANGE NOTICES/STATUS/CHANGE ORDERS<br />

" A change notice has been developed to replace the skin on the tent. DDI to be sent specs for tent<br />

fabric.<br />

" A change notice to revise electrical drawings will be submitted from WCH to DDI this week<br />